Installing the Product
English 8/2019. Rev 0.0
27
3.8
Preparation Stage—Visual Inspection
CAUTION
If any defects are found during the inspection, contact the SAMSUNG SDI customer service
department.
3.8.1
Inspection of the Rack Frame
After transporting the rack frame to the installation location, check for:
Structural damage
Paint peeling
Damaged or protruding screws.
After completion, install or package the rack for protection during storage.
3.8.2
Inspection of the Modules
After transporting the modules to the installation location, check for:
Physical damage to the exterior
Damaged or protruding screws
Proper voltage and internal impedance of the battery modules using the battery tester.
Table 3-8: Module Voltage and Internal Impedance
No.
Items
Value
1
Voltage Check
28.712 ~ 29.104V
2
Internal Impedance Check
3.0 ~ 4.3 mΩ
After completion, install the battery module in the previously installed rack or return the battery module to
its original packing for protection during storage.
3.8.3
Inspecting the SMU
After transporting the SMU to its installation location, check for:
Physical damage
Paint peeling
Damaged or protruding screws.
After completion, install the SMU in the previously installed rack or return the SMU to its original packing for
protection during storage.
Summary of Contents for 136S
Page 1: ...Confidential English 8 2019 Rev 0 0 LIB System for UPS Installation Manual 136S ...
Page 4: ...Confidential English 8 2019 Rev 0 0 ...
Page 10: ...Important Safety Instructions Confidential vi English 8 2019 Rev 0 0 ...
Page 18: ...Confidential Table of Contents viii English 8 2019 Rev 0 0 ...
Page 153: ...Confidential Memo ...
Page 154: ...Confidential Memo ...
Page 155: ...Confidential Memo ...
Page 156: ...www SamsungSDI com ...