17
Ins
tallation Pr
oc
edur
e
English
Refrigerant pipe before EEV kit and MCU or without EEV kit and MCU
•
You can contact the gas side and liquid side pipes
but the pipes should not be pressed.
•
When contacting the gas side and gas side pipe, use
1 grade thicker insulator.
Refrigerant pipe after EEV kit and MCU
•
Install the gas side and liquid side pipes, leave
10mm of space.
•
When contacting the gas side and liquid side pipe,
use 1 grade thicker insulator.
Gas pipe
Liquid pipe
Insulation
Insulation
Gas pipe
10mm
Liquid pipe
10mm
10mm
Step 10 Installing the drain hose and
drain pipe
1
Push the supplied drain hose as far as possible over the
drain socket.
2
Tighten the metal clamp as shown in the picture.
3
Wrap the supplied large sealing pad over the metal
clamp and drain hose to insulate and fix it with clamps.
4
Insulate the complete drain piping inside the building
(field supply).
If the drain hose cannot be sufficiently set on a slope, fit
the hose with drain raising piping (field supply).
5
Push the drain hose up to insulation when connecting
the drain hose to drain socket.
Metal clamp
Drain socket
Drain hose
Be sure to bond the drain
hose and the main pipe.
Drain pipe
Large seailng pad
Drain hose
PVC Tube Joint
+ VP25 (OD: 32 mm, ID: 25 mm)
Drain pipe
Summary of Contents for AE071MNMPEH
Page 40: ......