3
.
Installing the Product
English 8/2020. Rev 0.3
99
3.10.10 DC Link Cable Connection
1.
Connect the ground cables.
Figure 3-127: Grounding Points (2 EA)
NOTICE
Connect the rack ground wire with an M12 screw
.
Rack ground screws and cables are not
factory-provided and must be provided by the installer or customer.
The fastening torque should be 30Nm (300kgf∙cm)
.
45 mm Pitch