    S&C Instruction Sheet 659-555

Shipping and Handling

To lift and place the PureWave SMS-250 PCS, follow these 
procedures:

STEP 1. 

If spreader bars are used for lifting, make sure the 
spreader bar(s) are secured.

STEP 2. 

Arrange the hoist slings so the lifting forces 

 

are distributed equally. See Figure 3 for an 
illustration of lifting the PCS enclosure. The 
equipment must be lifted with a crane or forklift.

STEP 3. 

Avoid sudden starts and stops when lifting.

STEP 4. 

Properly place the PCS on the concrete pad. See 
Figure 4 for the location of cable entry conduit and 
mounting bracket installation areas. For further 
details, refer to drawing PEA-1610-4-IN and the 
other project-specific lifting drawings supplied 
with the PureWave SMS-250 system.

STEP 5. 

Remove the sling straps.

Figure 3. Proper lifting of the power conversion system  
enclosure.

Figure 4. Conduit and bracket measurements for pad-mounting.

This point should be at least 
45 inches (1143 mm) above 
the top of the PCS enclosure .

Dimensions are in 
inches (millimeters)

3 .50

(89 mm)

3 .24

(82 mm)

2 .00

(51 mm)

3 .83

(97 mm)

AC POWER CABLE 

ENTRY LOCATION

CONTROL & 

COMMUNICATIONS CABLING 

& WIRE ENTRY LOCATIONS

DC POWER CABLE 

ENTRY LOCATION

CD-1720 BRACKET

10 .80

(274 mm)

9 .17

(233 mm)

32 .00

(813 mm)

29 .00

(737 mm)

Summary of Contents for PureWave SMS-250

Page 1: ...placement Instructions and Labels 3 Location of Safety Labels 4 Trip Settings 5 Breaker Protection Curves 6 Safety Precautions 7 Shipping and Handling Packing 8 Inspection 9 Handling 9 Installation Assembly and Setup System Design 11 Concrete Pad Specifications 11 Pad Requirements 11 Shimming Grouting and Caulking the PCS Enclosure 12 Mounting 12 Cable Terminations 13 Battery Connection 13 Power C...

Page 2: ... inside a compartment in the PCS enclosure where they can be easily retrieved for future use Proper Application WARNING The equipment in this publication must be selected for a specific application The application must be within the ratings furnished for the equipment Failure to do so can result in damage to equipment Warranty The warranty and or obligations described in S C s standard conditions ...

Page 3: ...injury if instructions including recommended precautions are not followed NOTICE NOTICE identifies important procedures or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If you do not understand any portion of this instruction sheet and need assistance contact your nearest S C Sales Office or S C Authorized Distributor Thei...

Page 4: ...ngs The symbol represents the power on button When the button with the symbol is pressed the breaker places the equipment into a fully powered state Equipment grounding conductor The symbol represents the power off button When the button with the symbol is pressed the breaker dis connects the load side from the power source The ac breaker disconnects the ac output to theload A dc breaker to discon...

Page 5: ...A rms 16 68 ms Short circuit current maximum amps peak and duration ms 2280 A rms 16 68 ms Short circuit current breaking amps RMS and duration ms 0 Arms Short L1 L3 Short circuit current initial amps rms and duration of 16 7 ms or 1 cycle 1110 3 A rms 13 ms Short circuit current maximum amps peak and duration ms 1570 A peak 13 ms Short circuit current breaking amps RMS and duration ms 0 A rms Sho...

Page 6: ...ruction Sheet 659 555 Safety Information Breaker Protection Curves The power conversion system has a fixed output The ac breaker is configured at the factory with the following protection curve Current in Amperes ...

Page 7: ...heuseofthepadlockprovide protection against inadvertent contact with hazardous voltages 8 GROUNDING For grounding purposes the pro ceeding must be followed The PCS base ground bar in the cable termination area must be connected to a suitable earth ground for testing before energizing the unit and at all times when energized The overall ground system should be sufficient to limit the ground potenti...

Page 8: ...sion system enclosure ships in one piece See Figures 1 and 2 NOTICE The Human Machine Interface HMI computer and bat teries for the PureWave SMS 250 system are shipped separately Figure 1 The power conversion system enclosure Figure 2 Internal view of the power conversion system ...

Page 9: ...rawing PEA 1610 4 IN and any other project specific lifting drawings supplied with the PureWave SMS 250 system Lifting equipment such as spreader bars and hoist sling straps are provided by others To avoid damaging the PCS enclosure when placing it at the desired location observe normal recommended procedures as well as the following general instructions CAUTION The PCS installer must ensure ALL l...

Page 10: ...or the location of cable entry conduit and mounting bracket installation areas For further details refer to drawing PEA 1610 4 IN and the other project specific lifting drawings supplied with the PureWave SMS 250 system STEP 5 Remove the sling straps Figure 3 Proper lifting of the power conversion system enclosure Figure 4 Conduit and bracket measurements for pad mounting This point should be at l...

Page 11: ...f degree and should have a flatness within inch 3 175 mm The pad should extend beyond the edge of the enclosure by an adequate amount to prevent the pad from cracking or breaking when the Hilti Kwik Bolt TZ anchor bolts are installed to bolt the PCS enclosure to the pad Pad Requirements General Requirements The concrete pad contractor shall provide and be responsible fordeterminationandexecutionof...

Page 12: ...nt 300 ml Gray around the outer edge of the bottom flange where it meets the concrete pad to provide a seal around the base of the PCS The purpose of the caulk is to further prevent ingress of insects and debris into the enclosure Mounting STEP 5 Anchor the PCS enclosure to the concrete pad Use inch 10 mm diameter 2 inch 51 mm embed Hilti Kwik Bolt TZ anchors for each bracket The anchor brackets s...

Page 13: ...cttothenegative terminal on the PureWave SMS 250 system Note that battery voltage is floating from the earth reference The battery enclosure must be bonded as indicated in the Earth Reference and Bonding section on page 16 Power Connections Terminate the ac cables to the line inputs L1 L2 and L3 in the cable termination area The ac output of the SMS 250 neutral is not bonded to ground The input an...

Page 14: ...eferences for electronic signals All cable tray conduit and raceway systems installed to interconnect power control and communications wiring to and from the PureWave SMS 250 unit shall be electrically continuous by bonding together at each individual section Each individual cable tray conduit and raceway section including pull boxes junction boxes and outlet boxes shall be bonded to the facility ...

Page 15: ...4 IN and any project specific drawings supplied with the PureWave SMS 250 system Note any problems found and corrective actions applied Torques Check all factory and field bolted electrical connections inside the PCS enclosure and verify they are torqued to the proper tightness See Table 4 for torque requirements Base Covers Install the base covers if not already installed at the front and back fo...

Page 16: ...ke sure all edges are feathered before applying primer Pre Startup Checklist The pre startup checklist will be provided and should be reviewed and filled out by the installing contractor The document must be signed and faxed to S C Electric Company at 414 423 8766 Annual Inspections After the PureWave SMS 250 system is commissioned and the unit is online inspection and maintenance should be schedu...

Reviews: