Preparation Before Operation
24
Check that the UPS operates properly, and then proceed to step
⑦
.
MC
C
B
MC
C
B
Hold for 1 second.
⑥
Set MAIN MCCB to “ON”.
If power outage simulation test does not finish properly, check the following points.
Possible cause
Countermeasure
The battery connector is not
connected.
Connect the battery connector.
⇒
See §6.1 “Battery Connector Connection”.
The Forced Bypass switch is set to
“Bypass”.
Set to “Inverter”.
⇒
See the step
⑥
in §6.1 “Battery Connector Connection”.
“Green OUTPUT” does not light.
Press and hold
for 1 second.
⇒
See the step
③
in §8.3 “Outage Simulation Test”.
“Red ALARM” lights.
Contact your supplier.
Contact your supplier or SANYO DENKI when the “Red ALARM” lights or when the UPS does not
operate properly even if you perform the countermeasure above.
⑦
Press and hold
for at least 1 second.
This completes outage simulation test.
⑧
Set MAIN MCCB to “OFF”.
Buzzer
Musical trill
LEDs
All of the LEDs go off.
Buzzer
Silent
LEDs
Orange BACK UP
Off
Green ON/OFF
Lit
Green OUTPUT
Lit
Green INVERTER
Lit
LEDs
Orange BACK UP Blinking
↓
after 5 seconds
All of the LEDs go off
Set to “ON”.
⑧
Set to “OFF”.
Leave BATT MCCB set to “ON”.
Note
BATT MCCB is “ON”.