Planning, transport, installation
LASERTEC 40
Page 63
Final
inspection
It is imperative a final inspection is performed after the assembly of the
machine.
During this process follow the list of points and tick them off.
•
Check levels of all lubricants and top up as necessary. You will find
the necessary information in Initial commissioning (see
“Maintenance”).
•
Have all transport locks been removed?
•
Have all trim panels and safety features been fitted and are they fully
functional?
Checklist for final inspection
Load bearing capacity of the floor is adequate.
Necessary safety distances and working areas are met as per applicable
regulations.
Machine is stable and positioned and installed as per the applicable
regulations.
Electrical connection is fully checked and also all points in the check list for
the electrical connection have been taken into account and ticked off.
Gas connection completely checked.
All transport locks and transport equipment as well as all assembly aids
and tools have been removed.
All splash protection features and trim panels as well as splash protection
features are fitted.
All monitoring switches and safety switches are fully functional.
Levels in the central lubrication system and the hydraulic unit are
adequate.
All lines are free of leaks and secured against damage, e.g. by chaffing,
kinking, crushing, tearing, etc, including on movement by the axis slides.