Cast-in-place
concrete
Casting
mold
NOTICE
If the terrain structure is too uneven, soil has to be removed and the terrain has to be graded, if necessary.
NOTICE
The concrete foundations must be aligned flush on a gravel bed. The rack can only be installed properly, if all
foundations are correctly aligned and at the same level.
Maximum height tolerance within the foundations: ± 30 mm.
NOTICE
Also when using a cast-in-place foundation, make sure that the foundations are cast up to the same height.
Fig. 4.2.3.-1 (removing soil and grading the terrain structure)
Fig. 4.2.3.-2 (aligning the concrete foundations on a gravel bed)
Fig. 4.2.3.-3 (flush height cast-in-place foundation)