1.6. Commitment of the Personnel
Only people who give reason to expect that they will reliably do their job are allowed. Persons whose ability to react is
affected, for example by drugs, alcohol or medication, are NOT allowed.
•
Every person that is involved in the mounting of PvMax3 must have read and understood these Mounting Instructions,
especially chapter "1.4. Safety Information", as well as all relevant chapters regarding the corresponding operations.
•
These Mounting Instructions should always be kept available and easily accessible for all persons involved.
•
Only trained and instructed qualified and certified personnel are allowed to execute the operations mentioned in this
instruction manual.
•
Personnel that still is to be trained may only mount the PvMax3 system under the supervision of an experienced person.
1.7. Training of the Personnel
These Mounting Instructions are addressed to certified personnel qualified in the areas of transportation and loading,
mounting, disassembly and disposal, having the following qualifications:
•
The certified professionals must be capable of fulfilling the tasks they have been assigned with and must be able
to realize and avoid dangers on the basis of their professional formation, experience, expertise and their specific
knowledge of the relevant regulations.
•
The certified staff members must have the required knowledge of the guidelines regarding safety, accident prevention and
environmental protection, as well as of loading and unloading regulations that apply at the respective construction site.
•
The certified professionals have the driving licenses required at the specific construction site to be able to drive site
vehicles and operate construction machines.
We recommend the operator to insist on a confirmation in writing in each case.
1.5. Obligation of the Plant Owner / Operating Company
The plant owner ensures that all parts of these Mounting Instructions are readily available and handy at the plant.
The plant owner/operating company undertakes to only let people work at and in the striking distance of the plant who
•
have read and understood the parts of the mounting instruction that are relevant for the respective operations,
•
are familiar with the fundamental regulations on work safety, accident prevention and protection of the environment
•
and have been instructed in the safe handling of the plant (training course).
Before starting any mounting works, the plant owner/operating company designates
•
a supervising person and ensures that
•
the construction site is inspected using plans showing all supply lines (water, electricity, gas) and thus
•
the position of all underground supply lines and unstable ground without sufficient load-bearing capacities are
marked properly or sealed off with barriers.