70
Installation manual of system “bp408” - Electrical connection
7.7.4.3
Two-part group with two lines
Figure 50 shows the bus topology of a two-part group with two lines for hall calls.
By terminating at the two shaft ends, the line structure is maintained.
NOTE
!
Pay attention to the termination during commissioning. Usually only a single lift is
put into operation and the group connection is established later. In this case, the
termination must be adjusted (see individual control system).
Figure 49:
Example of topology of a two-part group with two lines
Summary of Contents for bp408
Page 2: ......
Page 24: ...24 Installation manual of system bp408 Safety instructions...
Page 52: ...52 Installation manual of system bp408 The control system bp408...
Page 58: ...58 Installation manual of system bp408 Installation and assembly...
Page 80: ...80 Installation manual of system bp408 Electrical connection...
Page 118: ...Installation manual of system bp408 Appendix 118 Appendix A Menu navigation bp408...
Page 119: ...119 Installation manual of system bp408 Appendix B Update of the firmware via USB stick...