Installation manual
Page 6 of27
2 Safety regulations
Intended use
You can only operate the PSCBR-E-133-12DI-2DIO-8RO module with an PSCBR-C-100.
This means that the same safety regulations apply as with the PSCBR-C-100 module.
2.1
Operation and service
The module must always be de-energized before installation and removal, or before
disconnecting signal lines. For this purpose all live supply lines to the device must be
checked for safe isolation from supply
When installing or removing the module appropriate measures must be applied to prevent
electrostatic discharge to the externally arranged terminal and plug connections. Contact with
such terminals should be reduced to a minimum and earthing by means of an earthing strap,
for example, should be carried out before and during these procedures.
2.2
Transportation/storage
Information concerning transport, storage and proper handling must be strictly followed.
The climate related specifications in chapter
“Technical data” must be complied with.