Assembly
Blow-out air:
For NSE3 and NSE-T3, by subsequently incorporating the
connection thread in the center of the plug. For clamping modules
with cone seal NSE3 99-K, NSE3 99-V1-K, NSE3 138-K, NSE3 138-
V1-K, NSE3 138-V4-K, NSE-T3 138, NSE-T3 138-V1-K, NSE-T3-K 138-
V4-K, direct connection via M7 connection thread: *
• 3 to max. 6 bar.
• The blow-out air must be switched off before the pallet is
placed on top, otherwise a pressure cushion may form or
vibrations may occur.
Recommendation:
– Switch off blow-off air → before placing the pallet (approx. 1
mm)
– Switch on blow-out air → only after lifting the pallet (approx.
1 mm)
*
NSE3 99, NSE3 99-V1 NSE3
138, NSE3 138-V1, NSE3 138-
V4, NSE3 138-P
Reworking on the plug
required.
*
NSE3 99-K, NSE3 99-V1-K,
NSE3 138-K, NSE3 138-V1-K,
NSE3 138-V4-K, NSE3 138-P-
K
M7 connection thread
integrated