Date Code 20011205
Close and Reclose Logic
6-11
SEL-311B Instruction Manual
SEL-311B(1) Relay
Before allowing circuit breaker 52/1 to be reclosed after an open interval time-out, the
SEL-311B(1) Relay verifies that Bus 1 voltage is hot and the transmission line voltage is dead.
This requires reclose supervision settings:
79CLSD = 0.00 cycles
(only one check)
79CLS = 3P59 * 27S
where:
3P59
= all three Bus 1 phase voltages (VA, VB, and VC) are hot
27S
= monitored single-phase transmission line voltage (channel VS) is dead
SEL-311B(2) Relay
The SEL-311B(2) Relay verifies that Bus 2 voltage is hot, the transmission line voltage is hot,
and in synchronism after the reclosing relay open interval times out, before allowing circuit
breaker 52/2 to be reclosed. This requires reclose supervision settings:
79CLSD = 0.00 cycles
(only one check)
79CLS =
25A1
where:
25A1
= selected Bus 2 phase voltage (VA, VB, VC, VAB, VBC, or VCA) is in
synchronism with monitored single-phase transmission line voltage (channel
VS) and both are hot.
Other Setting Considerations for SEL-311B(1) and SEL-311B(2) Relays
Refer to
Skip Shot and Stall Open Interval Timing Settings (79SKP and 79STL, Respectively)
in the following
Reclosing Relay
subsection.
SEL
OGIC
control equation setting 79STL stalls open interval timing if it asserts to logical 1. If
setting 79STL is deasserted to logical 0, open interval timing can continue.
The SEL-311B(1) Relay has no intentional open interval timing stall condition (circuit breaker
52/1 closes first after a transmission line fault):
79STL =
0
(numeral
0)
The SEL-311B(2) Relay starts open interval timing after circuit breaker 52/1 at the remote end
has reenergized the line. The SEL-311B(2) Relay has to see Bus 2 hot, transmission line hot, and
in synchronism across open circuit breaker 52/2 for open interval timing to begin. Thus,
SEL-311B(2) Relay open interval timing is stalled when the transmission line voltage and Bus 2
voltage are not in synchronism across open circuit breaker 52/2:
79STL =
!25A1
[=NOT(25A1)]
Summary of Contents for SEL-311B
Page 6: ......
Page 8: ......
Page 10: ......
Page 24: ......
Page 26: ......
Page 122: ......
Page 124: ......
Page 138: ......
Page 168: ......
Page 172: ......
Page 254: ......
Page 282: ......
Page 306: ......
Page 348: ......
Page 364: ......
Page 366: ......
Page 448: ......
Page 460: ......
Page 466: ......
Page 476: ......
Page 482: ......
Page 494: ......
Page 500: ......
Page 522: ......
Page 526: ......
Page 528: ......
Page 534: ......
Page 536: ......
Page 550: ......
Page 570: ......
Page 586: ......
Page 600: ......