(Figure 2)
Operation curve interface introduction:
Top heating temperature
: top heating temp. Correspond to the red curve.
Bottom heating temperature
: Bottom heating temp. Correspond to the yellow
curve.
Top heater setting
: top heater temperature setting.
Bottom heater setting
: bottom heater temperature setting.
IR temperature
: 3
rd
IR bottom heater temperature setting. Correspond to
green curve.
IR setting
: IR bottom heaters setting.
Real temperature (-1-2-3)
: shown current sensor temperature.
Run time
: recording the time from start to end.
Start
: Click start, starting heating.
Stop
: when machine is heating, click “Stop” to stop heating.
Manual Cooling
: Cooling system, switch control of the cooling system
between manual and automatic.
(Note: During the heating process, don’t allow to open the cooling system.)
Manual Vacuum
: vacuum button to control the vacuum.
Analysis
: Screen change button, control switch “curve analysis”.
BGA select
: Select the data stored in the database.
Save to USB
: there is USB connector, can insert USB and saving current
screen (BMP format).