Concrete
Foundation plate
to be levelled
60°~ clamp opening
Conduit
2) Foundation plate anchoring
−
Make a 500 x 500 x 300 mm (depth) hole in
the ground.
−
Widen the foundation plate clamps till they
reach approx. 60° (Fig. 3).
−
Fill the hole with R425 concrete and place the
foundation plate as shown in Fig. 3.
−
Accurately level the plate.
*
The middle hole of the plate must be used for
cable routing. Therefore, make sure that the
conduit connected to the hole complies with
current regulations, before filling the hole with
concrete.
Anchoring
nuts and
washers
Hole for the conduit containing
the electrical cables
3) Post anchoring on the foundation plate
−
Place the casing so that the holes on the base match the
screws located on the foundation plate.
−
Make sure that the conduit for the cables goes through
the large hole of the casing base.
−
Insert the bracket for anchoring the spring: A in case of
left-hand mounting, B in case of right-hand mounting; the
bracket must always be positioned towards the inside as
in Fig.4
−
Fix the casing on the foundation plate, screwing the
supplied nuts and washers carefully.