Assembly: Ballast Section
Components
Qty
Metal Centre Core
Ballast Rings 100kg
7
Duck Foot Plate
1
M20x 40mm Bolts
4
M20 Spring Washers
4
Check Components
Unpack all components from container. Inspect all components for any damage. Please alert Sealite if
any component is missing or damaged.
Assembly
Step 1
Lay centre core down, supported so end section
is clear of the plates to be installed.
Step 2
•
Duck Plate – take one ring and tack weld in six places, allowing
access to the four bolt holes on the underside.
• Slide the balance of the metal ballast rings over the core, leaving the
duck plate ring as the last one.
• Slide duck plate over core – ensuring the 4 x bolt holes align with the
bolt holes in core of pipe
• Fix M20 bolts in and tighten with torque wrench.
Complete fixed Ballast – should look as follows: