background image

PrimeTest 200

11

8.5.2

Plug the equipment under test (EUT) into the EUT socket  11  on the 
front of the PrimeTest 200.

8.5.3

Plug the black insulation test lead into the negative, black, socket  12 
on the PrimeTest 200.

8.5.4

Connect the other end of the black insulation test lead to any exposed
metal parts on the outer cover of the EUT or near the mains input or
mains switch if there are no exposed metal parts.

8.5.5

To start a Class  II safety test, press the       button  9 .

During an insulation resistance measurement a high voltage is
applied between the Live/Neutral of the EUT and the black test
probe. It should be noted that this voltage can also be present on
bare metalwork of the EUT.

8.5.6

The insulation resistance of the EUT is measured over a period of 2 
seconds. The large display 2 indicates a digital and analogue 
insulation M

, the small display  3  indicates a PASS/FAIL status. An 

additional visual display of a 

or  

also indicates PASS/FAIL status.

8.5.7

Insulation resistance value is held on the LCD display for a period of 1 
second. The displayed insulation resistance will flash if a FAIL and 
remain steady if a PASS.

8.5.8

The result will remain displayed until another rotary switch or pushbutton
action.

8.6

Touch Leakage Current,

See figure 8

Attention - before a touch leakage current test is performed on a 
Class II EUT the operator must ensure that the EUT has already 
passed a Class II safety test.

Attention - An RCD may be triggered if the EUT is defective.

Warning - It is important that the user verifies that an appliance with
moving parts (e.g. an electric drill) is safely mounted to allow
movement without causing damage to equipment or personnel. 

8.6.1

Plug the PrimeTest 200 into a mains power socket using the supplied 
IEC lead.

8.6.2

Select the touch leakage current test function on the rotary switch  10  . 
The LCD will display a probe signal to indicate that a safety test lead is
required.

8.6.3

Plug the equipment under test into the EUT socket 11 on the 
front of the PrimeTest 200.

8.6.4

Plug the black test lead into the negative, black socket  12  on the
PrimeTest 200.

8.6.5

Connect the other end of the black test lead to exposed metalwork
on the EUT.

8.6.6

When the         button   9   is pressed the PrimeTest 200 checks the wiring
of the power socket being used. If the line potentials are correct then the
LCD will display the symbols PE and PN in the steady state. Where a
fault exists then the  appropriate symbol will flash (see Appendix 2) along
with     symbol being displayed in the steady state. A fault condition will
inhibit the touch leakage test.

Operating Instructions

Summary of Contents for PrimeTest 200

Page 1: ...PrimeTest 200 Operating Instructions Bracken Hill South West Industrial Estate Peterlee Co Durham SR8 2SW England Tel 44 0 191 586 3511 Fax 44 0 191 586 0227 www seaward co uk sales seaward co uk cal...

Page 2: ...Operating Instructions Primetest 200 Operating Instructions Primetest 200 Operating Instructions Primetest 200 Fig 1 Fig 2 Fig 3 Fig 4...

Page 3: ...Operating Instructions PrimeTest 200 Fig 5 Fig 6...

Page 4: ...Operating Instructions PrimeTest 200 Fig 7 Fig 8...

Page 5: ...Operating Instructions PrimeTest 200 Fig 9 Fig 10...

Page 6: ...Operating Instructions PrimeTest 200 Fig 11...

Page 7: ...Operating Instructions PrimeTest 200 Fig 12B Fig 12A...

Page 8: ...PrimeTest 200 Operating Instructions...

Page 9: ...opying recording or in any manner without prior written consent from SEAWARD Electronic Limited This also applies to accompanying drawings and diagrams Due to a policy of continuous development SEAWAR...

Page 10: ...PrimeTest 200 Operating Instructions...

Page 11: ...otes These operating instructions are intended for the use of adequately trained personnel The PrimeTest 200 has been designed to make measurements in a dry environment It must not be used for making...

Page 12: ...ring function and insulation resistance measurement function M Electric shock danger Where safe operation of the tester is no longer possible it should be immediately shutdown and secured to prevent a...

Page 13: ...n up to 200 M resistance measurement 10 Measuring function selects the voltage up to 250 V AC DC measurement 11 Measuring function C selects the temperature up to 400 C measurement 4 2 LCD and Keymat...

Page 14: ...Test 200 is switched on from power off position to another switch position an on load battery test occurs The result of this test determines the available battery capacity A healthy battery results in...

Page 15: ...infinity Bargraph accuracy 10 Test voltage 500VDC at 1mA 750VDC for o c Test voltage accuracy 20 0 Test current 2mA for s c Input protection 0 5A 600 V quick blow fuse An input voltage of 30 V AC DC...

Page 16: ...current measurement Measuring Range Resolution Accuracy Overload Protection 3 5mA 0 01mA 10 2 digits 5 40 N A 15 2 digits 0 5 Test voltage mains supply 230V 15 10 10A max Frequency 50Hz 1 Test duratio...

Page 17: ...ck test lead to exposed metalwork on the EUT 8 1 6 To start a Class I safety test sequence press the button 9 8 1 7 The earth continuity resistance for the EUT is measured at 200mA The large display 2...

Page 18: ...the test is inhibited 8 2 5 To start the differential leakage test press the button 9 Mains power is applied to the EUT for a period of 2 seconds 8 2 6 Where a longer differential leakage test is req...

Page 19: ...o the PrimeTest 200 then PE and PN symbols will flash and the test is inhibited 8 3 5 The earth loop resistance is checked and an ohmic range selected on the large digital display This resistance valu...

Page 20: ...nt a high voltage is applied between the LIVE Neutral and common of the IEC lead 8 4 7 The insulation resistance of the lead is measured over a period of 2 seconds The large display 2 indicates digita...

Page 21: ...or pushbutton action 8 6 Touch Leakage Current See figure 8 Attention before a touch leakage current test is performed on a Class II EUT the operator must ensure that the EUT has already passed a Cla...

Page 22: ...display 3 will revert to indicating a PASS FAIL status An additional visual display of a or also indicates the PASS FAIL status 8 6 10 The touch leakage current will remain displayed until another ro...

Page 23: ...h potential Electric shock danger 8 8 1 Ensure the circuit or test object to be measured is voltage free Ensure the IEC mains lead is disconnected from the PrimeTest 200 8 8 2 Select the insulation re...

Page 24: ...ure 12a and 12b 8 10 1 Select the voltage measurement function on the rotary switch 10 8 10 2 Plug the voltage measurement adaptor into the IEC mains input plug 14 on the end of the PrimeTest 200 8 10...

Page 25: ...aning 9 3 1 Clean the external case of the PrimeTest 200 with a clean dry cloth 9 3 2 Avoid using solvents and abrasive scouring agents to clean the external case of the PrimeTest 200 9 3 3 Check the...

Page 26: ...be displayed 9 6 Checking the EUT Socket Fuses 9 6 1 Plug the PrimeTest 200 into the mains power socket using the IEC lead provided 9 6 2 Select one of the three power tests differential leakage curre...

Page 27: ...ery compartment and fasten in position with the battery cover captive screw 9 8 Calibration To maintain the specified accuracy of the measurement results the instrument must be recalibrated at regular...

Page 28: ...rence Positions 90 E1 N A Supply Voltage At the Limits Specified E2 0 52 by the Manufacturer Temperature 0 C and 35 C E3 1 Absorbed Current of Maximum Absorbed Current Device on Test of the Device on...

Page 29: ...90 E1 N A Supply Voltage At the Limits Specified E2 0 53 by the Manufacturer Temperature 0 C and 35 C E3 1 Absorbed Current of Maximum Absorbed Current Device on Test of the Device on Test E4 N A Low...

Page 30: ...ositions 90 E1 N A Supply Voltage At the Limits Specified E2 0 56 by the Manufacturer Temperature 0 C and 35 C E3 0 81 Absorbed Current of Maximum Absorbed Current Device on Test of the Device on Test...

Page 31: ...ons 90 E1 N A Supply Voltage At the Limits Specified E2 0 75 by the Manufacturer Temperature 0 C and 35 C E3 1 4 Absorbed Current of Maximum Absorbed Current Device on Test of the Device on Test E4 N...

Page 32: ...h Earth Open Circuit On Flash Flash Neutral Open Circuit Err 1 The PrimeTest 200 has failed one of the Earth Relay Pre Check tests Contact your local service agent Err 2 The PrimeTest 200 has failed o...

Page 33: ...PrimeTest 200 Operating Instructions...

Page 34: ...PrimeTest 200 Operating Instructions...

Reviews: