INSTALLING THE CONTROLLER CABLE

Connect one end of the MagIQtouch Controller cable (with 

ferrite suppressor) to the cooler electronics box.

Feed looped end of the controller cable (A) through the “wedge 

shaped” knockout and into the dropper. 

Important! 

Ensure cables do not interfere with the 

weatherdamper.

Note! 

It is important to route both cables out through the 

dropper grommet before fitting ductwork.

Installation of the cooler must conform to local electrical rules, 

regulations and standards.

Important!

 It is a requirement of Seeley International that 

all Breezair coolers be connected to a dedicated circuit to 

the distribution board, with a separate circuit breaker and 

incorporate a separate isolation switch in accordance with the 

local wiring rules.
A 10A socket outlet within one metre of the dropper’s cable exit 

hole is required.

The following specifications for the cooler electrical supply are 

required:
240V / 50 Hz Single Phase

WARNING!

 If the supply cord is damaged, it must be replaced 

by the manufacturer, its service agent or similarly qualified

ELECTRICAL REQUIREMENTS

Installation of the cooler water supply must conform to  

local plumbing rules, regulations and standards including  

AS/NZS 3500.1

The following specifications for the cooler water 

 

supply are required:

Water Connection

 

½” BSP

Min Water Pressure

 

100 kPa (15 psi)

Max Water Pressure

 

800 kPa (115 psi)

Min Water Flow

 

8 litres / min

Max Water Temperature 

40°C

Important! 

If the water pressure exceeds maximum 

specification then a pressure reducing valve is required 

 

and must be supplied and fitted by the installer.

Harmony & Horizon

For Coolers with the inlet solenoid valve fitted, the water 

connection is a 1/2” BSP compression fitting on the end of a 

flexible hose. This can fit directly onto the water pipe or be 

screwed directly onto the manual water shut-off valve. Always 

ensure that the water pipe connection does not place sideways 

strain onto the float valve.

Homemaker

A permanent water supply is required to be connected to the float 

valve. The water connection point is located on the underside 

of the cooler. The water connection fitting is a 1/2” BSP male 

adaptor suitable for a compression fitting. Do not fit the manual 

water shut-off valve directly onto the plastic nipple. You must 

install a manual 1/4 turn ball type shut off valve (do not use a 

stop cock) in the water supply line adjacent to the cooler, subject 

to local plumbing regulations. This allows the water supply to be 

isolated whenever work needs to be done on the cooler.

Important! 

In areas subject to freezing, the water supply line 

to the cooler requires a drain down facility at the lowest point in 

the water supply pipe. 

Important! 

Flush the water pipe to remove any swarf before 

final fitting. Swarf can lodge in the solenoid and float valve, 

preventing them from functioning correctly.

WATER REQUIREMENTS

Summary of Contents for Breezair EXQ

Page 1: ... English INSTALLATION MANUAL EXQ EZQ EXS Evaporative Coolers ILL1672 A Original English Instructions ...

Page 2: ...NG THE MAGIQTOUCH CONTROLLER 14 COMMISSIONING THE COOLER 14 DIAGNOSTIC LED 14 SALINITY LED 14 MAGIQTOUCH CONTROLLER INFORMATION 15 TESTING THE DIRECT DRIVE MOTOR 15 SETTING THE WATER LEVEL 15 TESTING THE DRAIN VALVE 16 REFITTING THE PAD FRAMES 16 TESTING THE PUMP 17 ADJUSTING COOLER SETTINGS 17 COMMISSIONING COMPLETION CHECKLIST 18 TROUBLE SHOOTING GUIDE 19 WARNING Failure to install and commissio...

Page 3: ...lty how can they summon help Call someone on the ground Mobile phone etc What condition is the roof in Should the trusses underside or surface be checked Does the worker have appropriate foot wear Flat sole jogger type is advisable Are all power cables extension leads safe and appropriately rated Are all ladders tools and equipment suitable in good condition Where ladders are to be used is there a...

Page 4: ...nt cooler to the dropper Check tank is level STEP 14 COMMISSION COOLER Test the cooler with the MagIQtouch Controller Check diagnostics of cooler electronics Test Direct Drive motor STEP 20 CLEAN UP Clean up the site STEP 3 PREPARE DROPPER Cut hole fit grommet in dropper for cables STEP 8 WEATHERDAMPER Check operation of the weatherdamper STEP 15 WATER LEVEL DRAIN Set the water level Test drain va...

Page 5: ...ng manually STEP 11 INLET SOLENOID Fit solenoid Connect cable Connect water supply Install drain pipe STEP 17 TEST PUMP Turn on cooler and check water is evenly distributed to all pads STEP 6 POWER CABLES Unhook the plug under the cooler Feed power cable down into dropper STEP 12 DRAIN VALVE Fit the drain valve Connect discharge system Connect cable to cooler electronics STEP 18 COOLER SETTINGS Wh...

Page 6: ...Always locate the cooler where it will receive adequate fresh air and not in a recess where it may be starved for air or where the air is polluted Ensure location is a minimum of 3m from a solid fuel heater flue 1 5m from a gas flue 5m from a sewer vent and 600mm from a wall The cooler must be mounted at least 3m preferably 5m away from any TV antenna or antenna cables Make sure the cooler is not ...

Page 7: ...r then fit and screw the cable grommet into position Locate the hole so the cables will not interfere with the operation of the weather damper Before transporting to the roof temporarily screw the transition to the dropper using a screw in each corner Affix gauge timbers under the top and bottom edges of the transition with 30mm screws supplied Keep the pallet to create a gauge for locating the tr...

Page 8: ... 3 sides This may require the addition of extra structural timber MOUNTING THE DROPPER Important The dropper must never sit directly on any ceiling joists or beams as this may cause noise or vibration issues and possible ceiling damage LEVELLING THE DROPPER TRANSITION Ensure the top of the dropper or transition for EZQ model is level and square in all directions use a spirit level This helps with ...

Page 9: ...ate the cooler on the dropper with the tank sump on the low gutter side of the installation Also remove the lower pads as they may fall out when transporting the cooler to the roof CONVEYING THE COOLER TO THE ROOF Lifting and installing the cooler is made easier by removing the pad frames first They can be replaced at the very end of the installation procedure Do not slide the cooler lift and carr...

Page 10: ... the roof squeeze the latch and rotate it clockwise to its operating position The weatherdamper latch performs two functions In the locked position it acts as a latch preventing movement during transport Important Ensure that the four Tab Screws which are removed to separate the transition from the cooler are re fitted behind the tabs after the cooler has been fitted into position Carefully lift t...

Page 11: ...Water Connection BSP Min Water Pressure 100 kPa 15 psi Max Water Pressure 800 kPa 115 psi Min Water Flow 8 litres min Max Water Temperature 40 C Important If the water pressure exceeds maximum specification then a pressure reducing valve is required and must be supplied and fitted by the installer Harmony Horizon For Coolers with the inlet solenoid valve fitted the water connection is a 1 2 BSP co...

Page 12: ...ank so it does not get trapped by the solenoid cover when fitted The cable leads can be connected to the solenoid either way around Important The cable must wrap underneath the solenoid Fitting the Solenoid Cover Once the solenoid valve and its cable has been fitted place the cover over the assembly Make sure the solenoid valve cable is retained in the groove in the cooler tank Secure the cover by...

Page 13: ... Connect the drain valve cable to the cooler electronics box HARMONY AND HORIZON DRAIN VALVE ASSEMBLY Assemble the drain valve as shown HOMEMAKER BLEED TRAY Fit the bleed tray as shown Screw the nut up tightly by hand underneath the cooler Do not overtighten Note Make sure the bleed tray is correctly oriented the bleed tray must sit underneath the Chillcel pad when it is fitted and that the o ring...

Page 14: ...le through our Sales order office and spare parts outlets in the following lengths Part No Length Details 833880 20m MagIQtouch Controller Cable No Ferrite 823553 20m MagIQtouch Controller Cable EXQ EXS With Ferrite 862873 1 5m MagIQtouch Controller Cable No Ferrite 861265 3m MagIQtouch Controller Cable No Ferrite 864396 30m MagIQtouch Controller Cable EXQ EXS With Ferrite 864402 40m MagIQtouch Co...

Page 15: ... the screen as they occur Current cooler operation information can be temporarily displayed on the Status Information Display option in the GENERAL SETTINGS menu When this option is turned on a temporary information display window becomes accessible on all MANUAL and PROGRAM screens TESTING THE DIRECT DRIVE MOTOR This Breezair cooler incorporates a Seeley electronically commutated Direct Drive Mot...

Page 16: ...be tested from the Service Operating Screen Set DRAIN to ON to energise the component and close the drain Set DRAIN to OFF to open the drain Alternatively the Manual Drain option in the COOLER SETTINGS menu can be used REFITTING THE PAD FRAMES Refit the pad frames by locating the bottom edge in the tank groove then push the top in under the lid Refit the corner clips after replacing the pad frame ...

Page 17: ...hen return to the set fan speed Prewet When COOL mode is activated the pump will run for 90 seconds before the fan is switched on Salinity Level Sets the salinity level at which the tank will drain in SALINITY MEASUREMENT mode Tank Drain Delay Sets the time delay before the drain valve opens after the pump in the cooler is turned off Autoclean Select the preferred cleaning interval 50 100 200 hour...

Page 18: ...ode ensure all pads have even water saturation and there are no visible water leaks COOLER SECURE The cooler is secure and level on the dropper using all fixings supplied SEALED The dropper and all penetrations are correctly flashed and sealed WEATHERDAMPER OPERATES The weatherdamper operates correctly and can open and close without interference PLUMBING FLUSHED The water pipes were flushed of any...

Page 19: ...ia the tri colour LED on cooler electronics box Rectify fault as indicated and restart the cooler MagIQtouch Controller failure Replace MagIQtouch Controller Pump runs but no water circulation Pump runs but pads lack water Insufficient water in tank Adjust float level Water hoses blocked Check and clean out blockage Pump strainer blocked Clean pump strainer Insufficient water supply pressure Check...

Page 20: ...rnational com service Spare Parts Information To identify and order spare parts for Seeley International products online go to seeleyinternational com get support spare parts It is the policy of Seeley International to introduce continual product improvement Accordingly specifications are subject to change without notice Please consult with your dealer to confirm the specifications of the model se...

Reviews: