SP LINK | Service Settings
96
|
Doc #OI0005 Rev26 2020
Schedule Restart
Sets the time when the SP PRO will perform an internal restart. This is normally used
in Off Grid systems, after new firmware has been loaded into the SP PRO. A restart
would normally cause loss of power so this can be set to occur at a time that is least
convenient to the customer, say 2:00 am.
Installer Only Service Settings
The settings in this group can only be changed WITH
an
Installer Only Code
OR within the first four (4)
hours of the SP PRO operation.
Normally these settings are configured at installation
and would remain unchanged. If a change is required
after the system has been running for longer than
four hours, an
Installer Only Code
is required. Once
entered, the code unlocks these settings for 5 minutes.
A code is available from Selectronic to bona fide
installers ONLY.
Anti Islanding Sensitivity reduces the active
anti islanding threshold in the SP PRO to provide
compatibility with some off grid and micro grid
systems. This setting must never be changed for
grid connected systems that require AS4777.2-2015
compliance.
The active anti islanding can be turned off completely
by setting the value to 0%.
Total Support Limit limits the maximum total power that can be taken from the battery plus the managed AC
Coupled Solar to support the customer’s load.
For example, if Total Support Limit is set to 5.0kW and there is 3kW of Solar being produced at the time, only
2kW of support power will be available from the battery, giving a total of 5.0kW
In multi-phase systems this setting is per phase.
Export Limit is the same function as a Factory Set Export Limit with the exception that it can be set by the
installer. If the Export Limit is set higher than any Factory Set Export Limit then the latter will apply.
In multi-phase systems this setting is per phase.
Allow Power Override enables the Power Override function within the Solar Hybrid Schedules. When set,
the Power Override setting will take a constant power (according to the Power Override setting in the active
Solar Hybrid schedule) from the batteries and push it out the AC Load port on the SP PRO.
Independent Grid Sync. This setting allows for the use of a single phase AC Source to be connected to the
L1 phase of a three phase Powerchain system. Either a single phase generator in a three phase off grid system
or a single phase grid supply feeding a three phase Powerchain system to provide three phase power (Single
phase to three phase converter).
This setting must never be enabled for three phase grid connected systems that require AS4777.2-2015
compliance.
AEMO Ride Through. This setting allows compliance to the Low Voltage Ride Through as specified by AEMO
in September 2020. This setting must be enabled when required by the local power network. For Example this
function is required by South Australian Power Networks (SAPN) so any grid connected system connected
within South Australia must have this setting enabled.
Summary of Contents for SP PRO 2i Series
Page 1: ...Instruction Manual for SP LINK Configuration and monitoring for SP PRO series 2i ...
Page 31: ...SP LINK Using SP LINK Doc OI0005 Rev26 2020 31 Blank Page ...
Page 91: ...SP LINK Performance Monitoring Doc OI0005 Rev26 2020 91 BLANK PAGE ...
Page 97: ...SP LINK Service Settings Doc OI0005 Rev26 2020 97 Blank Page ...