INSTALLATION | System Configuration
34
|
Doc #OI0003 Part #004122 Rev19 2014
DC couple Charge Controller Preparation
Before a DC coupled (charge current fed directly to the battery bank) renewable energy charge controller is
installed and integrated into the system the following requirements must be adhered to:
•All DC coupled
charge sources must be fed to the battery bank via an optional current shunt.
•All DC coupled charge controllers must have either an output that is activated when the charge
controller reaches float OR an input that triggers the charge controller to a float charge state.
Failure to install a current shunt or charge stage linking will reduce the performance and result in non
-optimal operation of the system.
For more detail on installing and integrating a DC charge controller refer to the relevant document in the
table below All documents found on the USB stick supplied with this inverter or on the support page of the
Selectronic web found site at www.selectronic.com.au
Document
Number
Document Name
Applicable charge
Controller
TN0045
SP PRO Shunt Installation
All Charge controllers
AN0002
SP PRO Renewable Regulator Integration
All CHarge controllers
TN0029
SP PRO PL Regulator Integration
Plasmatronics PL regulator
TN0031
SP PRO DINGO Regulator On Grid Export Integration
DINGO regulator
TN0030
SP PRO DINGO Regulator Float Integration
DINGO regulator
TN0033
SP PRO Outback Flexmax 60-80 Regulator Float
Integration
Outback Flexmax 60/80 regulator
Line diagram for DC Coupled Charge Controller Integration