background image

Page 9

76mm

(3”) min.

-Suitable lengths of chimney
-Stove Pipe Adapter
-Trim Collar
-Round Top

Flashing

Minimum
50mm 2”
air space
clearance

Universal
Roof
Brace Kit

Storm Collar

Locking
Band

Stove
Pipe
Adapter

Follow
Appliance
Instructions
for proper
connector
clearance

Support
Band

Cathedral
Ceiling
Support

Flue Pipe

Round Top

Figure 17

NOTE: The male coupler of the chimney length must be pointing
upwards as per the arrow on the chimney label.

The bottom chimney length should protrude into the living space so
that proper clearances are maintained at the adapter (see Figure 17).

The Cathedral Ceiling Support Box is manufactured to an over-
all outer dimension of 12” x 12” (305mm x 305mm).  Therefore,
the suggested framing to fit the box is 12-1/4” x 12-1/4” (311 x 311mm).

suspend the chimney below the roof.  To complete a proper
Cathedral Ceiling Support installation, the folllowing parts may
be required:
-Cathedral Ceiling Support /w 4 painted ceiling trim angles
-Roof Flashing w/ Storm Collar

The following instructions will assist you in the installation of
your chimney with a Cathedral Ceiling Support.  This support will
hold up to 30’ of chimney, of which 15’ can be suspended below
the box.  Chimney joints made below the support must be secured
with locking bands.

Wall Band

WALL BAND

The Wall Band is used along an outside wall at 8 ft intervals for
lateral stability.  Secure the Wall Band bracket to the wall using
two 6d or 2” spiral nails.  For concrete walls use suitable masonry
fasteners.The nut and bolt supplied will fasten the band around
the chimney.

Figure 16

After framing in your opening to the dimensions specified above
and in Table 1, slide the Cathedral Support Box into the joist/
rafter opening.  Once the box is at the desired location, ensure
the box is level and plumb.  Nail the box to the framing using four
2” spiral nails or equivalent per side.  The excess material stick-
ing above the roof can either be trimmed off before attaching the
box to the framing or, after it is installed the corners can be cut
and the excess material folded down onto the roof deck.

Install the Support Band on a chimney length at the desired

CATHEDRAL CEILING SUPPORT

A Cathedral Ceiling Support is  available for

 

5” and 6” diameters

chimney only.  For other diameters, a roof support can be used to

NOTE:

 Inverting the brackets (brackets mounted above the support

plate) can be accomplished by inserting extra  bolts through the
oblong slots of the support side brackets and the support plate
as per Figures 14 and  15.  Secure with nuts.  In this position, the
range of adjustability is limited to 5” from the wall.

Nuts

Slot on
Support
Bracket

Support Brackets

Pre-Punched
Holes of Support
Bracket

Support Plate
w/ Flange Up

Front Hole for
Retainer Clip

Slot on
Support
Plate

Bolts

FIG. 15- SLOT AREAS

WITH BOLTS AND NUTS
ASSEMBLY OF SUPPORT

BRACKET AND

SUPPORT PLATE

FIG. 14- FRONT VIEW OF

WALL SUPPORT

ASSEMBLY WITH

BRACKETS MOUNTED

ABOVE THE SUPPORT

PLATE

Summary of Contents for ULTRA-TEMP

Page 1: ...MATERIALS MODEL IT IS OF THE UTMOST IMPORTANCE THAT THIS CHIMNEY BE INSTALLED ONLY IN ACCORDANCE WITH THESE INSTRUCTIONS PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNINGYOUR INSTALLATION FAILURETO INSTAL...

Page 2: ...ZING FRAMINGDETAILS CEILINGSUPPORT ATTICINSULATIONSHIELD FIRESTOPJOISTSHIELD ELBOWINSTALLATION ADJUSTABLEWALLSUPPORT WALLBAND CATHEDRALCEILINGSUPPORT ROOFSUPPORT ROOFFLASHING UNIVERSALROOFBRACEKIT ROU...

Page 3: ...chimney passes Safety gloves Safety goggles Hammer and nails Tin snips Tape measure Scewdrivers and pliers Plumb line and level Square Keyhole say or power jig saw Caulking gun and caulking Be sure th...

Page 4: ...uld conform to Table 1 2 With the Lower Bucket removed place the upper bucket assembly into the framed opening from below 3 Ensure that the support plate is level and flush and drive one nail 1 1 2 co...

Page 5: ...le contact of this material with the chimney surface FIRESTOP JOIST SHIELD A Firestop Joist Shield must be installed where the chimney passes from one living space to another living space It is instal...

Page 6: ...sections must pass vertically through framed joist areas ELBOW INSTALLATION Elbow Kits 2 elbows 1 offset support and 4 locking bands FIGURE7 Attic Insulation Shield Storm Collar Elbow Locking Bands I...

Page 7: ...ified in the Framing Dimensions in Table 1 install the outer half with the unfinished square plate of the Insulated Wall Thimble in the outside wall opening Secure in place using appropriate fasteners...

Page 8: ...t Brackets Threaded Stud and Nut located at rear of Support Plate Pre Punched Holes of Support Bracket Flange Up Holes for Retainer Clips FIG 10 FRONTVIEW OFWALLSUPPORTASSEMBLY Support Plate 6 Ensure...

Page 9: ...the Wall Band bracket to the wall using two 6d or 2 spiral nails For concrete walls use suitable masonry fasteners The nut and bolt supplied will fasten the band around the chimney Figure 16 After fra...

Page 10: ...Brackets to the roof pitch and tighten nuts Attach to the roof with six 6 large wood screws per bracket with the inner most screws going into the rafters or headers See Figure 18 19 9 Additional chim...

Page 11: ...he flashing under the roofing shingles At least half of the flashing top and sides should be UNDER the shingles and the lower end OVER the shingles to provide a watershed Trimming off the shingles may...

Page 12: ...top surface of the length Wrap the band snug to the bottom of the 3 tabs and secure in place with the supplied nut and bolt The connection of a single wall base tee or single wall flue pipe or double...

Page 13: ...artment 4 Do not use salt or water on the fire Salt is corrosive and water will cause a dangerous steam explosion You may be able to control the fire by using ashes sand or baking soda since baking so...

Page 14: ...eter 8 Diameter 5 Diameter 30o OFFSET CHART Chimney Lengths 7 Diameter 6 Diameter 8 Diameter 5 Diameter none 6 12 18 24 12 18 36 12 36 18 36 12 18 36 48 OFFSET CHART CHIMNEY INSTALLATION It may be nec...

Page 15: ...affect its performance If you think a nearby obstacle could affect draft you might want to install one or more additional lengths CHART 2 CHIMNEY HEIGHT ABOVE THE ROOF DISTANCE FROM PEAK 10 Ft 9 Ft 8...

Page 16: ..._______________________________________ Address ______________________________________________________ City _________________________________________________________ Province _________________________...

Reviews: