UNLOADING/UNPACKING
Your new SEM shredder has been secured to a pallet for shipping. Please
inspect equipment immediately for shipping damage.
o
Using a lift truck with a minimum capacity of 1500 pounds, remove the
machine from the carrier and transport to operation site. Remove
pallet and discard responsibly. The feed tables and discharge hoop are
located in a box on top of the shredder pallet.
o
All light duty machines are equipped with casters for ease of handling.
o
Remove all guards and inspect interior of machine for shipping
damage. Check oil level in reducer (see fig. 3, page 21). Add oil if
necessary. See lubrication section on page 13.
o
After inspection, reinstall all guards including feed table and discharge
hoop. A bag must be installed in the hoop before starting to shred.
o
If an optional discharge conveyor was ordered with your machine, then
you must install it before beginning to shred. Be sure belt is tracking
properly after installation (see page 14).
NOTE:
This unit is shipped without a wall outlet plug. This is to simplify the
installation procedure – allowing the unit to be hardwired into a junction box
or to be fitted with the appropriate plug type.
NOTE:
This unit is available in three different voltage options (460 V, 220 V,
and 208 V). All units are 3 phase, and require 60 Hz.
Please confirm
power requirements prior to ordering.
5
Summary of Contents for 800-1000 Series
Page 19: ...Figure 1 SHREDDER OPERATION 19 ...
Page 20: ...Figure 2 CHAIN LUBRICATION 20 ...
Page 21: ...Figure 3 REDUCER LUBRICATION PN TA5215H40 21 ...
Page 22: ...Figure 4 CONVEYOR BELT TAKE UP 22 ...
Page 23: ...Figure 5 CHAIN SAG 23 ...
Page 25: ...Figure 7 DRIVE BELT ADJUSTMENT 25 ...
Page 35: ......