background image

- 21 -

115.6001.10

t.

 Install the chamber into the water bath tank in proper orientation and fasten in place with the eight
bolts around the top plate. Replace the rubber gasket if required.

u.

Insert a new lead gasket into the groove in the chamber flange.

v.

Install the chamber flange into the chamber.

w. Insert the twelve 3/4" bolts into the chamber flange and apply 110 FOOT-POUNDS TORQUE. Make

sure to torque opposite bolts sequentially.

x.

Reconnect wiring to anodes and ammeter. Refer to Cathodic Protection Section VIII.

y.

Insert gas temperature and pressure sensors into their protective wells.

z.

Prepare the vaporizer for startup. Refer to Pre-startup Section.

aa. Start up the vaporizer. Refer to Startup Section.

4.2.2

Replacement Criteria

After the chamber has been cleaned both inside and outside of all deposits and ferric chloride, the
chamber should be weighed and inspected for excessive corrosion pitting to determine if it is still
safe for continued use.

When new, the chamber weighs 200 pounds (90.7 kilograms) and has an inside diameter of 5.761"
(146.3 mm). the chamber should be replaced if it exhibits a loss over 15 pounds (6.8 kilograms), or if
any pitting deeper than 0.125" (3.17 mm) can be measured.

Any vaporizer chamber which does not exceed these losses can be considered safe for continued
use.

a.

Gas Filter

While the vaporizer is shutdown for chamber cleaning, it is advisable that the filter (Y-strainer or
cartridge) in the gas line between the vaporizer and the pressure reducing valve be
disassembled and cleaned. Refer to the manufacturer’s instructions.

1.

Loosen fasteners housing the strainer or cartridge.

2.

Wash the strainer in hot soapy water. discard the cartridge.

3.

Dry the strainer completely.

4.

Reinstall cleaned strainer or new cartridge using a new lead gasket.

4.3

Heater Replacement

If the vaporizer requires longer than normal warm-up times or, if the full vaporization capacity cannot be
achieved, one or more heating elements may have failed.

Before inspecting the heaters, check the fuses in the power supply for failure.

To inspect the heater elements, FIRST TURN ELECTRICAL POWER OFF to the vaporizer heater and control
circuit. Then open the door on the heater enclosure. Disconnect the two wires to each heater element and, using
an ohmmeter, measure the resistance across the terminals. Infinite resistance indicates a faulty heater. Refer to
Figure 10 and proceed as follows to replace the heater element.

4.3.1

Shut off the manual gas discharge valves downstream of the vaporizer and shut down the process
equipment.

4.3.2

Open the 1" drain valve and drain the water from the water bath tank. Close the valve when the tank is
empty.

4.3.3

Close the manual filling valve.

4.3.4

Open the heater enclosure door and disconnect the two wires to the bad heater element.

4.3.5

Using a 1-1/2“ socket wrench, unscrew the heater element. Remove the element and gasket.

4.3.6

Install the new heater element and gasket. Be sure the new element is the same electrical rating as the
old one, per the markings on both parts.

NOTE:

 The heater elements must be aligned vertically for proper operation. Note the “UP" molded in the

face of the heater at installation.

Summary of Contents for VAX4600 Series

Page 1: ...1 115 6001 10 Instruction Manual Vaporizer for Chlorine or Sulfur Dioxide Series VAX4600 CAPITAL CONTROLS...

Page 2: ...on to instruction operating manuals all instructions given on labels or attached tags should be followed Regardless of these efforts it is not possible to eliminate all hazards from the equipment or f...

Page 3: ...off Switch 23 4 6 Water Temperature Control Thermostat 23 4 7 High and Low Water TemperatureAlarm Switches 23 4 8 Cathodic Protection Anode Replacement 23 4 9 Recommended Torque Values 25 5 TROUBLESHO...

Page 4: ...115 6001 10 4...

Page 5: ...n The unit consists of a hot water tank a chemical vaporizing chamber a NEMA 4X heater control circuit a NEMA 4X water level control circuit chemical and hot water monitoring instruments cathodic prot...

Page 6: ...115 6001 10 6 Figure 1 Vaporizer Flow Diagram Figure 2 Chemical Boiling Points at System Pressure...

Page 7: ...o water condition The water level control switch is field wired to a solenoid valve in the water supply line providing automatic water level control The low water level alarm switch may be field wired...

Page 8: ...tion chamber is manufactured from 6 ASTM SA 53 B seamless carbon steel pipe All welds are in accordance with ASME boiler and pressured vessel codes Section VIII Division I Both inlet and outlet connec...

Page 9: ...9 115 6001 10 Figure 4 Cabinet Dimensions Utility Connection Locations...

Page 10: ...rsibly Prolonged operation under conditions of RF interference though not unsafe may damage some instrument components and is not recommended 1 4 Principle of Operation Liquid is transferred from its...

Page 11: ...ension requirements 2 2 Mounting Install the vaporizer on a mounting pad of concrete or other suitable material approximately 2 50 mm high Secure using 3 8 diameter bolts See Figure 4 for mounting hol...

Page 12: ...115 6001 10 12 Figure 6 Vaporizer Piping Connections...

Page 13: ...al gas liquid lines and water lines as shown in Figure 6 Plumbing must be in accordance with local codes When installing the nipples tees and 1 ammonia unions into the inlet and outlet ports of the ch...

Page 14: ...ve on the free end of the flexible connector and connect to the liquid valve of the chemical container 2 3 3 Water Line Connections See Figure 6 a Install 1 overflow piping to the outlet provided on t...

Page 15: ...e control circuit terminal block d Wire the water fill solenoid valve to the control circuit terminal block Do not apply power 2 4 3 Alarm Switches a The low water temperature alarm switch can be conn...

Page 16: ...ncy procedures Before continuing with the startup contact Capital Controls with questions or to arrange a training program if necessary 3 3 1 Start Up a Turn on the power to the heaters control circui...

Page 17: ...17 115 6001 10 Figure 8 Chlorine and Sulfur Dioxide Vaporizer Components...

Page 18: ...ine pressure induced by heat ton containers or induced by padding pressure tank cars operate on the gas phase of the source top container valve until the pressure drops to approximately 70 psig 483 kP...

Page 19: ...the instrument panel ammeter This should be read and adjusted weekly using the potentiometer knob directly below the ammeter A zero reading at all potentiometer settings indicates replacement of anod...

Page 20: ...zero and leave open 4 Disconnect the 1 union in the chemical liquid pipe at the vaporizer after the chemical liquid valve f Pass dry air into the vaporizer through the chemical liquid inlet at the di...

Page 21: ...reducing valve be disassembled and cleaned Refer to the manufacturer s instructions 1 Loosen fasteners housing the strainer or cartridge 2 Wash the strainer in hot soapy water discard the cartridge 3...

Page 22: ...ches Refer to Figures 3 and 4 If any of the final control elements are not functioning properly the cause may be a malfunctioning water level switch or water temperature control switch Refer to the wi...

Page 23: ...82 C Low Temperature Alarm Switch 170 F 77 C High Temperature Alarm Switch 190 F 88 C 4 8 Cathodic Protection Anode Replacement The water wetted surfaces of the vaporizer are protected against corrosi...

Page 24: ...115 6001 10 24 Figure 10 Replacing Heater Element...

Page 25: ...a W 4 n e p o e v l a v l l i f l a u n a M a h c t i w s l o r t n o c l e v e l r e t a W b y l n o l l i f c i t a m o t u a g n i n o i t c n u f l a m t o n d i o n e l o s e v l a v l l i f c i...

Page 26: ...115 6001 10 26...

Page 27: ...27 115 6001 10...

Page 28: ...e 05 06 CAPITAL CONTROLS Severn Trent Services 3000 Advance Lane Colmar PA 18915 Tel 215 997 4000 Fax 215 997 4062 Web www severntrentservices com E mail marketing severntrentservices com UNITEDKINGDO...

Reviews: