5
Single-point synchronization
Startup
Product Manual – MOVITRANS
®
TES31A Decentralized Supply Unit Synchronization
43
5.5.4
Synchronization procedure
To perform startup, proceed as follows:
Switch off power to network
Configure the SBus address
Connect supply system to slave
Configure the SBus address
Switch off power to network
Switch on the supply system
Startup completed
Set up necessary cabling for
network units
Disconnect the connections
X5161 and X2337
Switch on supply system of
designated master
Configure the synchronization
setting as "SP master"
Perform further
settings as required
Configure the synchronization
setting "SP Slave"
Connect load connections and
terminate interface X5161
If necessary, perform power
balancing
Further
slave
available
No
Yes
30903721483