59(60)
6.5 Maintenance Schedule
6.5.1 About the Machine
Model SN Manufacture date
Voltage
Ф
V Frequency Hz Power kW
6.5.2 Check After Installation
Check if the lockup screws of the fixed blades are locked firmly.
Check if the flange of the speed reducer has been locked firmly.
Electrical Installation
Voltage: V Hz
Specs of the fuse: 1 Phase A 3 Phase A
Check phase sequence of the power supply.
6.5.3 Daily Check
Check main power switch.
Check emergency stop button.
Check start / stop button.
Check material check plate (strip) is perfect or not.
Check whether emergency stop and safety switch works normally.
Clean feed box.
Check whether start, stop and power switches are normal.
6.5.4 Weekly Check
Check all the electrical cables.
Check if there are loose connections of electrical components.
Check whether set screws in fixed and rotate blades are under looseness.
Check if there is abnormal noise, vibration and heat in reduction gear.
Check the cracking window
6.5.5 Monthly Check
Check the status of the belt.
Check the overload protection function of the motor.
Check the tightness of the blades.
6.5.6 Check Half-yearly or Every 1000 Running Hours
Summary of Contents for Budget SG-24EB Series
Page 1: ...SG 24EB Series Budget Screenless Granulators Date Nov 2018 Version Ver A English ...
Page 2: ......
Page 33: ...33 60 2 4 Electrical Diagram ...
Page 34: ...34 60 ...
Page 35: ...35 60 ...
Page 36: ...36 60 ...
Page 37: ...37 60 ...
Page 38: ...38 60 ...
Page 39: ...39 60 ...
Page 40: ...40 60 ...