D 18/01/2011 J Shepherd
1 Fascia boards can now be drilled
and screwed ( fig 39 ) with 1x50mm
screw at each roof bearer and the roof
edgings. Wavy at the front plain at the
back
Fig 39
2 Drill diamond and screw with 2x50mm
screws .(fig 40)
Fig 40
1 The floor is fitted working from front
to back with
40mm nails
2 Position the first floorboard under
the doorframe (Fig 41), with the
groove against the wall.
Fig 41
3 Fix into position with two nails at each
floor bearer (Fig 42& 43)
fig 42
Fig 43
4 Continue with remaining floorboards
until you have three remaining.
5 Place these in position without nailing
them down, as the last floorboard will require
trimming.
6 Measure the distance between the last full
board and the wall (Fig 44). This measure-
ment is then marked on the final board and
then cut to Fit ,
leaving the groove on the
board
Fig 44
7. curl the boards up ( fig 45 ) to put it into
position and nail the remaining boards before
.
Fig 45
1 Place ring handle on the outside of the
door. Place the handle approx. half way
up the door (fig 46 ) making sure you are
central to the framework running across
the other side.
Fig 46
2 Mark the holes. Join the holes with a
marker (fig 47). Then drill at the top
corner point
but far enough in to clear
the screws
. (6mm Drill Bit).
fig 47
3 .
Place the wooden handle on the
inside of the door and screw from the
outside; using the hole just drilled
( fig 48 ) and 1x 45mm flat head screw.
Fig 48
4 Fix the ring handle, using 4x 25mm
black screws on the other side of the
door covering the screw for the wooden
knob.
5
Door catch
Fig 49
6 place the spring piece of the catch
level with the inside edge of the door and
fix with the screws provided ( fig 49 ).
Fig 50
7 With the door closed push the catch
together. and mark the required position
of the door catch housing. Secure using
2 x screws provided (fig 50 ).
fig 51
1 Push vents into holes provided (fig
51).
2 Fix CE plaque above front door.
3 screw narrow logs K (fig 51 ) into
position .
Fig 52
3 Fix the logs K.( fig 52 ) and fix the
terrace capping pieces V1 with 2 x
50mm screws each.( fig 53 )
Fig 53
4 Fix the V2 posts to the deck bearer
(fig 54) with 1 x 80mm screw and then to
the each log with 80mm screws
Fig 54
4 Trim off the corners of the capping
pieces (fig 55)
Fig 55
1 Place the clear plastic glazing material
into the aperture of each window.
2 Hold into position with four pieces of
beading . The beading may need to be
swapped around to get the best fit. When
satisfied secure into position using 2x
15mm panel pins per piece of beading.
( FIG 56 )Repeat for all window and door
apertures.
Fig 56
3.
Do not replace with glass.
J Fascia
K Floor
L Door furniture
M Finishing touches
N Glazing
1
Check and ensure that no raised grain or splinters are
evident on timber components. Sand down any raised
grain or splinters using fine grade sandpaper.
2
Check that all screw, nail and pin heads are properly
tapped home and are not proud of the timber surface.
3
Check and ensure that no screws, nails or pins protrude
through any panel.
4 Check and ensure that all parts are properly secured
against reasonable force.
5
Do not apply decorative wood finish/treatments to wet or
damp timber. Please observe the instructions of the wood
finish/treatment manufacturer.
6
6
Adults need to check the playhouse regularly and main-
tain the playhouse in good condition to provide a safe
play environment. Do not use if damaged. If damaged the
playhouse should be properly and safely repaired before
further use by children.
.
Assembly Completion Checklist