7
Commissioning
7.1
Overview
Prerequisites
•
Project planning is completed.
•
Mounting is completed.
•
Electrical installation is completed.
•
Dangerous state of the machine is and remains off during commissioning.
•
The outputs of the device do not affect the machine during commissioning.
•
The machine has been inspected and released by qualified safety personnel.
•
Protective device works properly.
•
The protection function is checked after each change to the machine or to the
integration or the operating and boundary conditions of the device.
Further topics
•
•
•
"Electrical installation", page 41
7.2
Switching on
Overview
After switching on, the sender and receiver initialize. All LEDs of the sender and receiver
briefly light up. After initialization, the receiver displays the alignment quality using four
blue LEDs. Once the safety light curtain is aligned (OSSD LED: green), the alignment
indicator switches off after a certain period of time, and only the PWR LED of the
sender and the OSSD LED of the receiver continue to light up.
In the event of a fault, the red fault LED flashes on the respective device. A red fault
LED in combination with the blue LEDs shows the cause of the fault on the side of the
receiver.
Further topics
•
7.3
Sender and receiver alignment
Overview
Once mounting and electrical installation are complete, the sender and receiver must
be aligned with each other.
Important information
DANGER
Dangerous state of the machine
b
Make sure that the dangerous state of the machine is (and remains) switched off
during the alignment process.
b
Make sure that the outputs of the safety light curtain do not affect the machine
during the alignment process.
7
COMMISSIONING
44