1) To perform the general operation, follow the stand-alone
operating requirement.
2) Startup: The units transfer to INV mode simultaneously as they
start up sequentially in Line mode.
3) Shutdown: the units shut down sequentially in INV mode.
When the last one completes the shutdown action, each unit
will shut down the inverter simultaneously and transfer to
Bypass mode.
It is easy to operate the equipment, with no previous training. You
just need to read through this manual and operate according to the
instructions in it.
Parallel Installation Diagram
Summary of Contents for Green Point 6 20KVA
Page 28: ...IV319 Rev 00 Data 2010 06 22 Pag 28 di 118 Wiring diagram of 6K 10K 1 1 parallel system...
Page 29: ...IV319 Rev 00 Data 2010 06 22 Pag 29 di 118 Wiring diagram of 10K 3 1 parallel system...
Page 57: ...IV319 Rev 00 Data 2010 06 22 Pag 57 di 118 DB 9 Interface of AS400 communication protocol...
Page 61: ...IV319 Rev 00 Data 2010 06 22 Pag 61 di 118 Back View of 15K 20K 3 1...