Mechanical properties of the motors
3.3 Flange forms
1FT7 Synchronous Motors
Configuration Manual, (PFT7S) 01/2009, 6SN1197-0AD13-0BP2
61
Commissioning
When required, before connecting the motors and converters to the cooling circuit, the pipes
should be flushed in order to avoid dirt entering the motors and converters.
After the units have been installed in the plant, the coolant circuit must be commissioned
before the electrical systems.
3.3
Flange forms
Table 3- 9
Flange forms
Designation
Representation
Description
Flange 0
Flange 0, recessed
1FT7⃞⃞⃞-⃞⃞⃞⃞0-⃞⃞⃞⃞
Flange 1
Flange 1,
compatible with 1FT6 motors
1FT7⃞⃞⃞-⃞⃞⃞⃞1-⃞⃞⃞⃞