7SR105 Rho Performance Specification
© 2018 Siemens Protection Devices
Chapter 3 Page 15 of 17
Table 1-24
50 Instantaneous & DTL OC&EF
Operation
Non directional
Elements
Phase, Derived Earth, Measured Earth
Setting Range I
s
(50/50N)
0.05,0.06…50xI
n
Setting Range I
s
(50G)
0.01, 0.011,.... 5xI
n
Time Delay
0.00…14400 s
Operate Level I
op
100 % I
s
, ± 5 % or ±1 % xI
n
Reset level
≥
95 % I
op
Reset level (50G)
≥ 95 % I
op
or I
op
- 0.1 % I
n
Operate time:
50, 50G
#
50N
0 to 2xI
s
– 35 ms, ± 10 ms,
0 to 5xI
s
– 25 ms, ± 10 ms
0 to 2xI
s
– 40 ms, ± 10 ms,
0 to 5xI
s
– 30 ms, ± 10 ms
Operate time following delay
t
basic
+t
d
, ± 1 % or ± 10 ms
Inhibited by
Binary or Virtual Input
Inrush detector
Disengaging time (50G)
< 50 ms
NOTE:
# The operating timings are measured on the basis of fundamental measurement algorithm, with protection
functions and communication ports configured in the relay.
Table 1-25
51 Time Delayed OC&EF
Operation
Non directional
Elements
Phase, Derived Earth, Measured Earth
Characteristic
IEC-NI, -VI, -EI, -LTI; ANSI-MI, -VI, -EI; DTL
Setting Range I
s
(51/51N)
0.05,0.06…4xI
n
Setting Range I
s
(51G)
0.01,0.011,...0.5xI
n
Time Multiplier
0.01, 0.015....1.6, 1.7,....5, 6...100
Time Delay
0,0.01… 20 s
Operate Level
105 % Is, ± 4 % or ±1 %xI
n
Minimum Operate time
IEC
ANSI
[ ]
Tm
K
t
Is
I
op
×
−
=
1
α
[ ]
Tm
B
A
t
P
Is
I
op
×
+
−
=
1
± 5 % absolute or ± 40 ms
for TMS setting (0.01 to 0.245)
± 5 % absolute or ± 30 ms
for TMS setting (0.25 to 100)
Follower Delay
0 s to 20 s
Reset
ANSI decaying, 0 s to 60 s
Inhibited by
Binary or Virtual Input
Inrush detector
Summary of Contents for 7SR105 Rho
Page 1: ...Answers for energy 7SR105 Rho User Manual Motor Protection Relay Reyrolle Protection Devices ...
Page 2: ...Siemens Protection Devices 2 ...
Page 95: ...7SR105 Rho Technical Manual Chapter 4 Page 2 of 70 2018 Siemens Protection Devices ...
Page 99: ...7SR105 Rho Technical Manual Chapter 4 Page 6 of 70 2018 Siemens Protection Devices ...
Page 127: ...7SR105 Rho Technical Manual Chapter 4 Page 34 of 70 2018 Siemens Protection Devices ...
Page 153: ...7SR105 Rho Technical Manual Chapter 4 Page 60 of 70 2018 Siemens Protection Devices ...
Page 155: ...7SR105 Rho Technical Manual Chapter 4 Page 62 of 70 2018 Siemens Protection Devices ...
Page 157: ...7SR105 Rho Technical Manual Chapter 4 Page 64 of 70 2018 Siemens Protection Devices ...