7SV512
Installation instructions
V1
47
C53000---G1176---C91
5.2.5 Checking the connections
!
Warning
Some of the following test steps are carried
out in the presence of hazardous voltages.
They shall be performed by qualified per
sonnel only which is thoroughly familia
with all safety regulations and precaution-
ary measures and pay due attention to
these.
Non-observance can result in severe per
sonal injury.
Before initial energization with supply voltage, the
relay shall be situated in the operating area for at
least two hours in order to ensure temperature
equalization and to avoid humidity influences and
condensation.
--- Switch off the circuit breaker for the d.c. supply
circuits!
--- Check the continuity of the current transformer
circuits against the plant and connection dia-
grams:
D
Are the current transformers correctly earthed?
D
Are the polarities of the current transformer cir-
cuits correct?
D
Is the phase relationship of the current trans-
formers correct?
--- If test switches have been fitted in the secondary
circuits, check their function, particularly that in
the ”test” position the current transformer sec-
ondary circuits are automatically short-circuited.
--- Fit a d.c. ammeter in the auxiliary power circuit;
range approx. 1.5 A to 3 A.
--- Close the battery supply circuit breaker; check
the polarity and magnitude of the voltage at the
terminals of the unit or at the connector module.
--- The measured current consumption should cor-
respond to approximately 7 W. Transient move-
ment of the ammeter pointer only indicates the
charging current of the storage capacitors.
--- The unit starts up and, on completion of the run-
up period, the green LED on the front comes on,
the red LED gets off after at most 5 sec.
--- Open the circuit breaker for the d.c. power supply.
--- Remove d.c. ammeter; reconnect the auxiliary
voltage leads.
--- Check through the tripping circuits to the circuit
breakers.
--- If multiple bus-bar is used, ensure that the distri-
bution of the bus-bar trip command depending
on the bus-bar disconnector position of all feed-
ers is correct.
--- Check through the control wiring to and from oth-
er devices.
--- Check the signal circuits.
--- Reclose the protective m.c.b.’s.