881-4027.9 * INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 * Revision 04
65
Top view
Fig77. Several views of deep bottom pan
4.3.9.2. Control cable connection
Internal wiring
The circuit diagrams for connecting the control cables are included in the low-voltage
compartment.
Remove main wiring duct covers on left inner side of switching device compartment.
Install connections from the foundation through the main wiring duct into the low-
voltage compartment.
Refit main wiring duct covers.
Connect control cables according to circuit diagrams.
Interconnection wiring between the switchgear and the other location
The control cables coming from outside to the switchgear are put into the channel. The
following drawings mention the foundation detail and the channel inside of the panel.
1
2
3