9.4 BACnet
9.4.1 Commission the BACnet/IP module
Participating devices
−
Climatix controller POL6XX.
−
Communication module POL908.
Participating tools:
−
Operator unit (HMI).
−
PC with web browser.
P3933Z27
BACnet / Ethernet IP
POL908 / POL6XX
HMI
PC
SCOPE
WEB
The SAPRO application (MBRCode.bin) is fully commissioned.
The BACnet/IP module is connected to the bus and configured. Procedure:
Step Action
1
Controller
OFF
.
2
Connect BACnet/IP module to the controller via plug connection.
3
Connect the BACnet/IP bus cable to the module.
4
Controller
ON
:
The module starts / initialization begins.
As soon as the two LEDs "BSP" and "BUS" are steady green, com-
munication with the controller and bus (BACnet) is active.
Caution:
HMI must be reset a second time to update; prior to parameterization.
5
Enter BACnet settings via HMI and web browser.
6
Configure BACnet/IP module.
Devices
Tools
Illustration
Prerequisite
Commission BACnet/IP
module
Basis Document Siemens Climatix Control System
BDCX.100820.01GB
Page 128