Configuration
4.2 Configuration in STEP 7
CP 154xSP-1
54
Operating Instructions, 12/2019, C79000-G8976-C426-05
Overview of configuration of the CP
Follow the steps below when configuring:
1.
Create a STEP 7 project.
2.
Insert the required SIMATIC stations from the following catalog directory:
Controller > SIMATIC ET200 CPU > ET 200SP CPU
3.
Insert the CPs and the input and output modules from the following catalog directory into
the stations:
Distributed I/O > ET 200SP
You can configure a maximum of two CP 154xSP-1 for an ET 200SP.
4.
Create an Ethernet network.
5.
Connect the stations to the Ethernet subnet.
6.
Configure the inserted CPs.
When the device view of the CP is open, you can find the BusAdapters in a separate
catalog directory.
You will find detailed information about the security functions in the section Security (CP
7.
Optional: Create the program blocks for the Open User Communication.
8.
Save and compile the project.
Here you will find information on individual parameter groups in the following sections. You
will find information on parameters not described in this manual in the information system of
STEP 7.
Downloading the configuration data
When you load the station, the project data of the station including the configuration data of
the CP is stored on the CPU.
You will find information on loading the station in the STEP 7 information system.