Commissioning
Localization and device testing
6
32 | 42
Building Technologies
A6V10349616_i_en_--
Fire Safety
2019-01-18
6 Commissioning
The device is commissioned via the control panel. The exact procedure is
described in the control panel documentation.
Conduct a performance check once commissioning is complete.
6.1 Localization and device testing
The manual call points have an internal alarm indicator. This alarm indicator may
as well be activated from the control panel for localization and device testing.
The LED indicator of the alarm indicator has the following meanings:
LED indication
Meaning
Off
●
Normal condition
Green
Flashes once per second
●
Test mode is active
Red
Flashes once per second
●
Localization is active
o r
●
Alarm is triggered
Red and green alternating
Flashes twice per second
●
Alarm is triggered/localization is active
a n d
●
Test mode is active