Installation
100/293
Revision 11 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • 802-9081.9
14
Unloading and erecting the switchgear
14.1
Packing and transport unit
Packing
The transport units can be packed as follows:
• On pallets, covered with PE protective foil
• In a seaworthy crate (switchgear is sealed with desiccant bags in PE foil)
• Other packings in special cases
Transport unit
Transport units consist of:
• Individual panels, if applicable with separate low-voltage compartment
• Accessories including busbars
14.2
Completeness and transport damages
Checking for
completeness
➭ Check whether the delivery is complete and correct using the delivery note and packing
lists.
➭ Compare the serial number of the switchgear panels on the delivery note with that on the
packing and the rating plates of the panels.
➭ Check whether the accessories are complete.
Checking for transport
damages
➭ Temporarily open the packing in a weatherproof place to detect hidden damages. Stick the
PE foil together again and do not remove it totally until reaching the final mounting position
in order to keep the switchgear as clean as possible.
➭ Check the ready-for-service indicator for SF
6
gas (see page 105, "Checking the ready-for-
service indicator").
➭ Inform the forwarding agent immediately about any defects or transport damages; if
required, refuse to accept the delivery.
➭ As far as possible, document larger defects and transport damages photographically;
prepare a damage report and inform your regional Siemens representative immediately.
➭ Have the transport damages repaired, otherwise you may not start installation.
➭ Refit the packing.
NOTICE
Disposal of packing and consumables
Incorrectly disposed of packings and consumables can pollute the environment.
➭ Packing and consumable materials of the switchgear must be disposed of in an
environmentally compatible way or recycled.
➭ Observe local regulations for disposal and environmental protection.