Automation system
222
System Manual, 12/2017, A5E03461182-AE
Commissioning
11
11.1
Overview
Introduction
This section includes information on the following topics:
●
Check before powering on for the first time
●
Removing/inserting the SIMATIC memory card
●
First power-on of the CPU
●
First power-on of the ET 200MP on PROFINET IO
●
First power-on of the ET 200MP on PROFIBUS DP
●
Operating modes of the CPU
●
CPU memory reset
●
Identification and maintenance data
Commissioning requirements
Note
Performing tests
You must ensure the safety of your plant. You therefore need to perform a complete
functional test and the necessary safety checks before the final commissioning of a plant.
Also allow for any possible foreseeable errors in the tests. This avoids endangering persons
or equipment during operation.
Software tools for commissioning
The following free software tools support you in commissioning:
●
SIEMENS PRONETA in commissioning PROFINET systems.
●
SIMATIC automation tool in commissioning the Automation System S7-1500 / Distributed
I/O System ET 200MP.
You can find more information on SIEMENS PRONETA and the SIMATIC Automation Tool
in the section Software (Page 87).