Commissioning
7
When carrying out any work on the machine, observe the general safety instructions
(Page 15) and the specifications contained in EN 50110‑1 regarding safe operation of electrical
equipment.
Note
Service Center
Please contact the Service Center (Page 137), if you require commissioning support.
7.1
Preparing for commissioning
Once the system has been correctly installed, you should check the following prior to
commissioning. It may be necessary to perform additional checks and tests in accordance with
the situation specific to the particular place of installation.
● The motor has been assembled and aligned properly.
● All mounting bolts, connecting elements and electrical connections are firmly tightened.
● The operating conditions correspond to the data specified on the rating plate.
● The bearings have been regreased as appropriate for the model.
● The machine is connected so that it rotates in the direction specified
● The cover sheets have been remounted correctly to ensure effective cooling of the motor.
● The rotor is fully able to turn and does not contact other parts at any point during rotation.
● All electrical and mechanical connections are secure. The function is assured.
● Any supplementary motor monitoring devices have been correctly connected.
● Appropriately configured control and speed monitoring functions ensure that the motor
cannot exceed the permissible speeds specified on the rating plate.
● If the motor is operated continuously under light-load conditions of I < 50 %, there is a risk
of high brush wear or problems with the commutator. Please consult the manufacturer if
this type of operation is intended.
The power output elements have the proper setting conditions according to type, for
example:
– Couplings are aligned and balanced.
– The belt tension is properly adjusted if there is a belt drive.
– Gear tooth flank play and gear tooth tip play, as well as radial play, are properly adjusted
if there is a gearwheel output.
● The minimum insulation resistance values are within tolerance.
● If the bearings are insulated, the insulation has not been bridged.
SIMOTICS DC 1GG6
Operating Instructions 02/2016
63
Summary of Contents for SIMOTICS DC 1GG6
Page 2: ...08 02 2016 10 27 V4 00 ...
Page 12: ...Table of contents SIMOTICS DC 1GG6 12 Operating Instructions 02 2016 ...
Page 14: ...Introduction 1 1 About these instructions SIMOTICS DC 1GG6 14 Operating Instructions 02 2016 ...
Page 70: ...Commissioning 7 8 Switch off SIMOTICS DC 1GG6 70 Operating Instructions 02 2016 ...
Page 82: ...Operation 8 9 Faults SIMOTICS DC 1GG6 82 Operating Instructions 02 2016 ...
Page 104: ...Maintenance 9 2 Repair SIMOTICS DC 1GG6 104 Operating Instructions 02 2016 ...
Page 138: ...Service and Support SIMOTICS DC 1GG6 138 Operating Instructions 02 2016 ...
Page 142: ...Quality documents SIMOTICS DC 1GG6 142 Operating Instructions 02 2016 ...
Page 153: ......