User data backup/Series commissioning
15.5 SINAMICS S120 standard commissioning with STARTER
Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
549
15.5
SINAMICS S120 standard commissioning with STARTER
A project must be available, created or loaded from a drive unit into the programming device
for the standard commissioning of SINAMICS S120. This project is loaded as a reference
project in the other drive units still to be commissioned.
Requirements
The following requirements must be fulfilled:
●
The reference drive unit is fully configured.
●
You can create an online connection to all drive units.
●
The reference project is loaded into the STARTER.
Implementation
Perform the following actions in the STARTER for each drive unit to be commissioned:
1.
Create a backup copy of the project: Project > Save as
2.
Access the drive unit online: Project > Connect to target system
3.
Load the project into the drive unit: Target system > Download > To target device
The drive unit applies the serial number from the previously located components in the
reference topology. This results in an inconsistency, which is displayed in the project
navigator.
4.
Read the project back into the programming device: Target system > Load > Load fully
into the programming device (all p and r parameters)
5.
Save your project: Project > Save
The configuration is now consistent again, i.e. the same project states exist in the target