Prepare area of work: Preparing a surface appropriate to electrostatic sensitive devices (EGB). In addition
to this, the following tools are required:
–
screwdriver with a 5 mm to 6 mm wide tip,
–
a Philips screwdriver size 1,
–
5 mm socket or nut driver.
•
Unfasten the screw-posts of the D-subminiature connectors on the back panel at location “A” and “C”. This
activity does not apply if the device is for surface mounting.
•
If the device has additional communication interfaces at locations “A”, “C” and/or “B” “D” on the rear, the
screws located diagonally to the interfaces must be removed. This activity does not apply if the device is
for surface mounting.
•
Remove the caps on the front cover and loosen the screws that become accessible.
•
Remove the front panel and tilt it to the side.
Work on the Plug Connectors
!
CAUTION
Mind electrostatic discharges
Non–observance can result in minor personal injury or material damage.
²
Electrostatic discharges over connections of components, conductor paths or pins are to be avoided by
prior touching of grounded metal parts at any circumstances.
²
Do not plug or withdraw interface connections under power!
The following must be observed:
•
Disconnect the ribbon cable between the front cover and the C-CPU-2 board (No. 1 in Figures
and
) at the front cover side. To disconnect the cable, push up the top latch of the plug
connector and push down the bottom latch of the plug connector. Carefully set aside the front cover.
•
Disconnect the ribbon cables between the C-CPU-2 board (1) and the I/O boards ((2) and (3), (depending
on the variant ordered).
•
Remove the boards and set them on the grounded mat to protect them from ESD damage. In the case of
the device variant for panel surface mounting, please be aware of the fact that a certain amount of force
is required in order to remove the C-CPU-2 module due to the existing plug connectors.
•
Check the jumpers according to
and the following information, and as the case
may be change or remove them.
The allocation of the boards for housing size
1
/
3
and for housing size
1
/
2
Mounting and Commissioning
3.1 Mounting and Connections
SIPROTEC 4, 7VE61 and 7VE63, Manual
147
C53000-G1176-C163-3, Edition 10.2017
Summary of Contents for SIPROTEC 4 7VE61
Page 8: ...8 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 24: ...24 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 142: ...142 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 192: ...192 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 222: ...222 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 230: ...230 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 256: ...256 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 314: ...314 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 316: ...316 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...
Page 330: ...330 SIPROTEC 4 7VE61 and 7VE63 Manual C53000 G1176 C163 3 Edition 10 2017 ...