Mounting and Commissioning
3
This chapter is intended for experienced commissioning staff. The staff must be familiar with the commissioning
of control systems, with power systems management and with the relevant safety rules and guidelines. Under
certain circumstances, it may become necessary to adapt parts of the power system hardware. Some of the
primary tests require the protected line or equipment to carry load.
Mounting and Connections
Checking Connections
Commissioning
Final Preparation of the Device