Control During Operation
246
7SS52 V4 Manual
C53000-G1176-C182-3
Figure 6-31
Window
Test - 4500 COMMUNICATION WITH CENTRAL UNIT
To put the bay for the busbar protection out of service, click the function
Switching
bay out of service
and click
Run...
. Next a password prompt takes place.
To take the bay for the busbar protection into service, click the function
Switching
bay in service
and click
Run...
. Next a password prompt takes place.
Enter the correct password in the box named
Password
and then click
OK
. If the
password is wrong, you will receive an error message. When the password is cor-
rect, the bay will be put out of service.
Note
A warm restart normally takes place after the reconnection of a branch. During the
shutdown, the warm restart is omitted as long as the connection continually exists and
if the parameters of the central processing unit and the field unit continue to coincide.
www