In the example in figure 2-6 is for a
PROT. OBJECT
=
Autotransf.
the side S3 the
tertiary winding, thus the accessible and load capable compensation winding. In this
example the setting would be:
Address
243
SIDE 3
=
compensation
.
This option is only possible for
PROT. OBJECT
=
Autotransf.
.
In the examples of figure 2-7 for
PROT. OBJECT
=
Autotr. node
side 3 is facing
the earthing electrode of the transformer. Here:
Address
243
SIDE 3
=
earth.electrode
.
This option is only possible if
PROT. OBJECT
=
Autotransf.
or if
PROT. OBJECT
=
Autotr. node
, if no further side has been assigned.
The same applied to address
244
SIDE 4
=
earth.electrode
In summary we can say: the sides S1 and S2 are imperatively assigned to the connec-
tions of the auto-connected winding. For
SIDE 3
and
SIDE 4
you have to select the
option corresponding to the topology:
auto-connected
(for another tap of the auto-
connected winding),
compensation
(for an accessible and load-capable compensa-
tion winding) or
earth.electrode
(for the earthed side of the auto-connected wind-
ings).
Assignment of Aux-
iliary 1-phase Mea-
suring Locations
Each of the auxiliary (1-phase) current inputs must now be assigned in the addresses
251
to
254
. The number of auxiliary inputs depends on the device type (cf. Table 2-
1). In 7UT635 all inputs
I
X1 to
I
X3 are only available as additional 1-phase measuring
inputs if they are not needed for a fifth 3-phase measuring location, i.e. if only four 3-
phase measuring locations are needed.
The auxiliary inputs can be assigned to a side or a measuring location, or they can
remain non-assigned. If you have assigned exactly one measuring location to a side,
this side is equivalent to the measuring location.
Single-phase auxiliary measured currents are used in the following cases:
1. In differential protection, to include the starpoint current of an earthed transformer
winding (either directly or via a neutral earthing reactor in the protected zone);
2. In restricted earth fault protection, to compare the starpoint current of an earthed
winding (transformer, generator, motor, shunt reactor, neutral earthing reactor)
with the zero sequence current from the phase currents;
3. In earth fault overcurrent protection, to detect the earth fault current of an earthed
winding or neutral earthing reactor;
4. In single-phase overcurrent protection, to detect any 1-phase current ;
5. For operational limit monitoring tasks and/or display of measured values.
Summary of Contents for SIPROTEC 7UT613 series
Page 16: ...Contents 16 7UT613 63x Manual C53000 G1176 C160 2 Literature 631 Glossary 623 Index 633 ...
Page 30: ...1 Introduction 30 7UT613 63x Manual C53000 G1176 C160 2 ...
Page 506: ...A Appendix 506 7UT613 63x Manual C53000 G1176 C160 2 7UT633 D E ...
Page 508: ...A Appendix 508 7UT613 63x Manual C53000 G1176 C160 2 7UT633 P Q ...
Page 510: ...A Appendix 510 7UT613 63x Manual C53000 G1176 C160 2 7UT635 D E ...
Page 512: ...A Appendix 512 7UT613 63x Manual C53000 G1176 C160 2 7UT635 P Q ...
Page 515: ...A 2 Terminal Assignments 515 7UT613 63x Manual C53000 G1176 C160 2 7UT633 B ...
Page 517: ...A 2 Terminal Assignments 517 7UT613 63x Manual C53000 G1176 C160 2 7UT633 N ...
Page 519: ...A 2 Terminal Assignments 519 7UT613 63x Manual C53000 G1176 C160 2 7UT635 B ...
Page 521: ...A 2 Terminal Assignments 521 7UT613 63x Manual C53000 G1176 C160 2 7UT635 N ...
Page 622: ...A Appendix 622 7UT613 63x Manual C53000 G1176 C160 2 ...
Page 632: ...Literature 632 7UT613 63x Manual C53000 G1176 C160 2 ...