1. SCOPE
This procedure includes information on the following connector types
•
SpecTRON 5 ROV Plugs
•
SpecTRON 5 ROV Receptacles
•
SpecTRON 5 Penetrators
•
SpecTRON 5 ROV Dummy Connectors (Plugs & Receptacles)
•
SpecTRON 5 ROV Parking Receptacle
Any information, records or Health and Safety feedback that needs to be detailed, can be recorded
in the punch list at the rear of the document
2. HEALTH & SAFETY
Manual Handling, Lifting and Carrying are known to be the largest contributors to occupational ill-
health.
Ensure that mechanical handling aids are used whenever possible to avoid manual handling.
Where manual handling is considered appropriate for the task safe lifting guidelines must be
followed, e.g. adopt correct posture, consider team lifting, employ safe lifting technique, etc.
Only competent persons are permitted to perform tasks without supervision, if in doubt ask.
Good Housekeeping avoids Slips Trips and Falls, keep your area clean and tidy.
It is the operator’s responsibility to comply with current Company & regional health and safety
legislation.
Caution shall be exercised during assembly to ensure that fittings and hydraulic / pneumatic
equipment are properly installed.
In the event of a safety incident or any safety improvement suggestions, please contact the Health &
Safety Department at
and/or complete and return the punch list in
section 11.0.
Note
– All receptacle’s (male pins) must be mated to its correct mating half before it is energised
(this includes the correct Test, Dummy and Wet Mate Pair).