13/148
Siemens Building Technologies
Commissioning instructions OZW775 V2.01
CE1C5663en
HVAC Products
Recommended commissioning
22.06.2012
2 Recommended
commissioning
2.1 Checklist
The following tables provide step-by-step descriptions to commission and parameterize
the system.
Experienced technicians may use the following tables like checklists to commission and
parameterize Synco devices using the ACS software. Less experienced technicians are
advised to read the referenced section.
Step
Section
Description
1
2.2
Prior to commissioning
2.2.1
Central communication units V1.0
"Update firmware".
2.2.2
Central communication units V2.0
Ethernet Yes/No, web server Yes/No.
2.2.3
Plant and devices ready for commissioning
2.2.4
Insert Ethernet card
If communication via Ethernet.
2.2.5
Direct connection of PC/laptop via USB
Connection for commissioning and parameterization.
2.2.6
Central communication unit ready for commissioning
Turn on AC 24 V (and AC 230 V) operating voltage.
2
2.3
ACS plant operating software
2.3.1
ACS software version
Check version in "Readme.txt" file.
2.3.2
Download ACS software
Uninstall old ACS software version and install new version.
2.3.3
Start ACS software
Log in using "Service" user level password.
3
2.4
Central communication unit firmware
2.4.1
Check firmware version
Version is available in data point "Software version".
2.4.2
Update firmware
CF card OZZ7CF required.
4
2.5
Web server function
2.5.1
Prepare web server data
CF card OZZ7CF required.
2.5.2
First login in the web brows).
First login via
User name: Administrator
Password: OZW775
2.5.3
Change password and language
New password, new language.
2.5.4
Add user
User name, password, language, user group.
Introduction