35/148
Siemens Building Technologies
Commissioning instructions OZW775 V2.01
CE1C5663en
HVAC Products
New plant
22.06.2012
3 New
plant
•
All commissioning steps described in Chapter 2 were carried out.
•
The ACS software was started and the user logged in via the "Service" level
password.
You must first create a new plant before you can begin commissioning and parameteri-
zation. This applies if:
•
You are using a new central communication unit V2.0
and if
•
you are using an original central communication unit V1.0 with a firmware update to
V2.0.
Once you update a central communication unit V1.0 to firmware version V2.0, it is no
longer backward compatible. Possible parameter set backups can no longer be used.
3.1 Create new plant
1. Select
Plant > New > Plant…
to create a new plant.
2. Enter the plant name in the "File name" field, e.g.
Building West
and click
Save
Prerequisites
Note
Workflow