Parameterize OZW775
22.06.2012
4.6 Application [ Popcard ]
Commissioning mode = On
Many data points are displayed in Application [ Parameter Setting ] and [ Popcard ]
"Commissioning mode = On" as well as [ Popcard ] "Commissioning mode = Off".
Data point "Wiring test active" is the only data point for commissioning that is displayed
only in Application [ Popcard ] "Commissioning mode = On".
4.6.1 Data points in the "Commissioning" operating page
Command sequence: Commissioning > Commissioning mode
Data point
Explanation, example
Commissioning mode
Default val: Off
Setting val: Off, On
Setting value "Commissioning mode = On" in
Applications [ Popcard ] provides access to the
command "Wiring test".
See also Section 5.1.1 on "Commissioning
mode On/Off".
Command sequence: Commissioning > Wiring test
Data point
Explanation, example
Wiring test active
Default val: No
Setting val: No, Yes
Setting value "Commissioning mode = On" (see
above) and "Wiring test = Yes" allows for
checking inputs N.X1…N.X8 and N.D1…N.D8
as well as the outputs for Time switch 1…4 and
Fault relay 1…2.
See also Section 5.2 on "Wiring test".
Commissioning mode
Wiring test