UTMC OTU/MOVA Handbook
667/HB/31601/000
Page 24
Issue 5
PRE-INSTALLATION CHECKLIST
STEP
FUNCTION
REFERENCE
1
Check unit supplied is as per works order
WORKS ORDER
2
Check unit contains correct IO cards.
WORKS ORDER
3
Check unit has the correct firmware loaded
into the Flash memory.
INSTALLATION CHECKLIST
STEP
FUNCTION
REFERENCE
4
Set up card address switches
5
Set up modem power selection
7
Set up 120/230V AC operation selection
8
Enable RTC battery and confirm the
watchdog link is correctly installed
9
Install unit and connect safety earth lead to
cabinet earth point
10
Connect digital IO
11
Complete post installation check
12
Identify all connectors/cable forms
13
Connect all connectors to the unit
–
14
Connect the unit to mains outlet
15
Switch on unit supply
–
16
Connect unit support battery
7
17
Commission the application
THE REST OF SECTION 4 TAKES YOU THROUGH THE STEPS IN THE
INSTALLATION CHECKLIST (above) IN MORE DETAIL…
Section 4.2 takes you through the steps that ‘configure’ the hardware before the unit is
installed.
Sections 4.3, 4.4 and 4.5 take you through the steps to install the unit.
And finally, section 4.6 takes you through all the steps involved in connecting up all the
various interfaces to the unit.
4.2 SET-UP
The unit, prior to its installation and commissioning, requires configuring for the type of
application, either on site or at a depot.
The hardware has a number of options as follows, which require selection before power
is applied to the unit…