Closing checklist
Once the charger has been commissioned, the unit requires
re-assembly and closing prior to operation.
Follow these steps in order to ready the unit for operation:
1. Remove lifting straps
Carefully remove the lifting straps from the top slots in the
metalwork.
2. Attach service cover
Place the Service Cover over the switch gear, and ensure it sits
flush with the metalwork panel, prior to fastening with screws
with a 2.5mm hex bit. If it doesn’t sit flush, remove and ensure
the wiring is sitting behind the lower face of the switch gear.
3. Attach service hatch over service cover
Check the gasket has not been damaged or soiled. If using a
power drill to fasten the nuts, ensure the correct torque
setting of not greater than 2.0 Nm/17.70 lb-in.
If using a hand tool, fasten until resistance felt. Do not over
tighten.
4. Re-attach radiator (if required)
• Angle the radiator and rest on the baseplate.
• Re-connect the four-way connector.
• Re-connect cooling hoses by pressing the metal parts
together, and ensure they are sitting out of the way, to avoid
pinching the hose or obstructing the radiator.
CAUTION
Ensure there is no leakage at this point.