INSTALLATION INSTRUCTIONS:
Ground Preparation
ArmorDeck is designed to be installed over synthetic grass, natural grass, gravel, sand, dirt, and
mud. No ground preparation is required for athletic fields or other level and consistent
surfaces.
It is recommended that a survey of the installation site be done prior to installation of
ArmorDeck. Larger stones, rocks and obstacles should be removed.
While ArmorDeck will span smaller indentations and gradations, it is recommended that large
holes be covered or filled with sand to create a more level finished floor.
Material Staging
Much of the time spent installing portable flooring involves shuttling material into position for
connection. In this regard it is advisable to use rolling carts, pallet jacks and/or forklifts where
possible to facilitate rapid placement of material. Specific attention should be paid to site
access and strategic placement of material pallets to minimize the distance traveled between
material pallets and the installation area.
Connecting Individual ArmorDeck Modules
An ArmorDeck floor consists of individual ArmorDeck modules connected to create a larger
floor. Unlike other flooring systems, Signature’s ArmorDeck features an integrated connection
system which is self-aligning and provides ease of installation and tremendous strength.
Sections are simply laid into place and self-align using Signature’s proprietary hook and loop
fastening system, which actually guide panels into place. For added strength, sections may be
locked together using Signature’s aluminum cam lock system, though in many applications the
basic hook and loop system will suffice and the cam need not be engaged.
Installing and ArmorDeck Floor
Begin installation of ArmorDeck by placing the first couple of sheets of flooring in the upper
right corner of the area to be floored. This piece will serve as the cornerstone onto which the
floor will be built. The female receptor loops should be on the inward facing sides of the sheet,