Installing the System into a Rack
007-6307-001
17
Installing the Outer Rails
Do the following to install the outer rails:
1.
Measure the distance from the front rail to the rear rail of the rack.
2.
Attach a short bracket to the front side of the right outer rail and a long bracket to the rear
side of the right outer rail.
3.
Adjust both the short and long brackets to the proper distance so that the rail can fit snugly
into the rack.
4.
Secure the short bracket to the front side of the outer rail with two screws and the long
bracket to the rear side of the outer rail with three screws.
5.
Repeat steps 2-4 for the left outer rail.
Installing the Server in a Rack
Warning:
Fully loaded, the ISS3104 server weighs about 43 lbs (19.5 kg). Always use
proper lifting techniques when your move the server. Always get the assistance of another
qualified person when you install the sever in a location above your shoulders. Failure to do
so may result in serious personal injury or damage to the equipment.
You should now have rails attached to both the chassis and the rack unit. The next step is to install
the server into the rack. Do the following as shown in
Figure 3-3
:
1.
Align the rear of the chassis rails with the front of the rack rails.
2.
Keeping the pressure even on both sides, slide the chassis rails into the rack rails.
You may need to depress the locking tabs when inserting. When the server has been pushed
completely into the rack, you should hear the locking tabs click.
!
Summary of Contents for InfiniteStorage 3104
Page 1: ...SGI InfiniteStorage Server 3104 ISS3104 User Guide 007 6307 001 ...
Page 3: ...007 6307 001 iii Record of Revision Version Description 001 December 2013 Original printing ...
Page 4: ......
Page 8: ......
Page 10: ......
Page 12: ......
Page 36: ......
Page 47: ...Replacing a Power Supply 007 6307 001 31 Figure 5 1 Replacing a Power Supply Module ...
Page 54: ......
Page 58: ......
Page 62: ......
Page 64: ......